What is project crashing and what are three reasons why it might be important to do so?

Correct Answer

verifed

verified

The process of accelerating a project is...

View Answer

Networks are adaptable and useful for all scheduling challenges that an organization faces.

Correct Answer

verifed

verified

Determine early start and early finish times for all activities in this network.Activity duration in days appears under each arrow. Determine early start and early finish times for all activities in this network.Activity duration in days appears under each arrow.

Correct Answer

verifed

verified

Early start and earl...

View Answer

An activity of duration zero whose sole purpose is to maintain network logic is a(n)________.

Correct Answer

verifed

verified

The most common type of logical sequencing between tasks is referred to as the:


A) finish to start relationship.
B) finish to finish relationship.
C) start to start relationship.
D) start to finish relationship.

Correct Answer

verifed

verified

In order to accelerate completion of a project,the manager must crash critical path activities.

Correct Answer

verifed

verified

Use the Gantt chart and the activity list to determine when resource 2 is free. Use the Gantt chart and the activity list to determine when resource 2 is free.     A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 Use the Gantt chart and the activity list to determine when resource 2 is free.     A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60


A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60

Correct Answer

verifed

verified

Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?   A) 10 minutes B) 15 minutes C) 0 minutes D) 5 minutes


A) 10 minutes
B) 15 minutes
C) 0 minutes
D) 5 minutes

Correct Answer

verifed

verified

Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.     A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.     A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2


A) Resource 4
B) Resource 3
C) Resource 1
D) Resource 2

Correct Answer

verifed

verified

Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.     A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4 Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.     A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4


A) Resource 2
B) Resource 3
C) Resource 1
D) Resource 4

Correct Answer

verifed

verified

Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.

Correct Answer

verifed

verified

The logical relationship between the start and finish of one activity and the start and finish of another activity is the ________.

Correct Answer

verifed

verified

The primary drawback with ________ occurs when the project is very complex,with numerous paths through the model.

Correct Answer

verifed

verified

A finish to start lag delay is usually shown:


A) as an added value in the predecessor's activity time.
B) on the line adjoining the two activity nodes.
C) as an added value in the predecessors early start time.
D) as a subtracted value in the follower's early finish time.

Correct Answer

verifed

verified

What is the early start time for activity C if it has the start to start relationship shown? What is the early start time for activity C if it has the start to start relationship shown?   A) day 20 B) day 25 C) day 27 D) day 29


A) day 20
B) day 25
C) day 27
D) day 29

Correct Answer

verifed

verified

Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.     A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3 Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.     A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3


A) Resource 2
B) Resource 4
C) Resource 1
D) Resource 3

Correct Answer

verifed

verified

Use the Gantt chart and activity list to determine which resource has the greatest continual use. Use the Gantt chart and activity list to determine which resource has the greatest continual use.     A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5 Use the Gantt chart and activity list to determine which resource has the greatest continual use.     A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5


A) Resource 4
B) Resource 2
C) Resource 3
D) Resource 5

Correct Answer

verifed

verified

Which of these approaches will NOT accelerate the completion of a project?


A) Improve the productivity of existing project resources.
B) Increase the bureaucratic oversight.
C) Improve the working method.
D) Increase the quantity of personnel and equipment.

Correct Answer

verifed

verified

For large projects,network diagrams are more useful if they are completely detailed.

Correct Answer

verifed

verified

Mick has a project consisting of eight activities as listed in the table (with durations in days).He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Determine the early and late start and finish times for all of these activities. Mick has a project consisting of eight activities as listed in the table (with durations in days).He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Determine the early and late start and finish times for all of these activities.     Mick has a project consisting of eight activities as listed in the table (with durations in days).He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Determine the early and late start and finish times for all of these activities.

Correct Answer

verifed

verified

The table ...

View Answer