The first step in level material use is to combine orders into a few large batches in order to utilize economies of scale.

Correct Answer

verifed

verified

A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. All dates are specified as days from Day 1.  Start day 1 Data  Received  Time  Due Date  A 12025 B 11520 C 1716D12550 E 1177 F 11332\begin{array} { | r | r | r | r | } \hline \text { Start day } & 1 & & \\\hline \text { Data } & & & \\\hline & \text { Received } & \text { Time } & \text { Due Date } \\\hline \text { A } & 1 & 20 & 25 \\\hline \text { B } & 1 & 15 & 20 \\\hline \text { C } & 1 & 7 & 16 \\\hline \mathrm { D } & 1 & 25 & 50 \\\hline \text { E } & 1 & 17 & 7 \\\hline \text { F } & 1 & 13 & 32 \\\hline\end{array} a. Complete the following table. Show your supporting calculations below. b. Which dispatching rule has the best score for flow time? c. Which dispatching rule has the best score for work-in-process (jobs in the system)? d. Which dispatching rule has the best score for lateness?  Dispatching  Rule  Average  Flow Time  Average Number  of Jobs  Number of  Jobs Late  Average  Lateness  FCFS  SPT  LPT  EDD  SLACK  CR \begin{array} { | l | l | l | l | l | } \hline \begin{array} { l } \text { Dispatching } \\\text { Rule }\end{array} & \begin{array} { l } \text { Average } \\\text { Flow Time }\end{array} & \begin{array} { l } \text { Average Number } \\\text { of Jobs }\end{array} & \begin{array} { l } \text { Number of } \\\text { Jobs Late }\end{array} & \begin{array} { l } \text { Average } \\\text { Lateness }\end{array} \\\hline \text { FCFS } & & & & \\\hline \text { SPT } & & & & \\\hline\text { LPT } & & & & \\\hline \text { EDD } & & & & \\\hline \text { SLACK } & & & & \\\hline \text { CR } & & & &\\\hline\end{array}

Correct Answer

verifed

verified

a)
blured image b) SP...

View Answer

Find the sequence for the priority rules of a. LPT b. SPT c. EDD Given the table below and the fact that today is the 1st  job  Process Time  Due Date  A 64 B 42 C 25 D 31\begin{array} { | l | l | l | } \hline \text { job } & \text { Process Time } & \text { Due Date } \\\hline \text { A } & 6 & 4 \\\hline \text { B } & 4 & 2 \\\hline \text { C } & 2 & 5 \\\hline \text { D } & 3 & 1 \\\hline\end{array}

Correct Answer

verifed

verified

a. ABDC
b....

View Answer

A work centre had planned outputs of 10,15,13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. The cumulative deviation in output is


A) 0.
B) 1.
C) -1.
D) 58.
E) unable to determine with given information.

Correct Answer

verifed

verified

Lockport Marine Services, Inc. wishes to assign a set of jobs to a set of machines. The following table provides data on the cost of production of each job when performed on a specific machine. a. Determine the set of assignments that maximizes production value. b. What is the total production value of your assignments?  Machine  Job  A  B  C  D 127292830230292726331252926429312528\begin{array} { | l | l | l | l | l | } \hline & { \text { Machine } } \\\hline \text { Job } & \text { A } & \text { B } & \text { C } & \text { D } \\1 & 27 & 29 & 28 & 30 \\2 & 30 & 29 & 27 & 26 \\3 & 31 & 25 & 29 & 26 \\4 & 29 & 31 & 25 & 28 \\\hline\end{array}

Correct Answer

verifed

verified

(a) The optimal set of assignm...

View Answer

The most appropriate sequencing rule to use if the goal is to dynamically track the progress of jobs and establish relative priority on a common basis is


A) shortest processing time.
B) earliest due date.
C) critical ratio.
D) longest processing time.
E) Johnson's rule.

Correct Answer

verifed

verified

Which of the following statements regarding finite capacity scheduling (FCS) is false?


A) Finite capacity scheduling is well suited for dynamic scheduling environments.
B) Finite capacity scheduling overcomes the disadvantages of systems based exclusively on rules.
C) Finite capacity scheduling is very powerful, but does not allow for rapid changes.
D) Finite capacity scheduling often gets its data from the output of an MRP system.
E) None; all of the above are true.

Correct Answer

verifed

verified

Explain, in your own words, what is meant by "level material use." In what types of facilities is it appropriate? Explain.

Correct Answer

verifed

verified

It means frequent, high quality, small l...

View Answer

Which of the following statements regarding scheduling at Air Canada is false?


A) About one flight in twenty is disrupted by weather events.
B) Schedule changes at one airport have a ripple effect that may have impacts in many others.
C) Delta's high-tech computer and communications system is located in Atlanta.
D) Delta's rapid rescheduling uses mathematical scheduling models.
E) Delta's rapid rescheduling promotes air safety and limits traveler inconvenience, but has not resulted in money savings for Delta.

Correct Answer

verifed

verified

Forward scheduling


A) begins with a delivery date, then offsets each operation one at a time, in reverse order.
B) is well suited where the supplier is usually able to meet precise delivery dates.
C) tends to minimize work-in-process inventory.
D) assumes that procurement of material and operations start as soon as requirements are known.
E) produces a schedule only if it meets the due date.

Correct Answer

verifed

verified

Bob Dresser operates a major appliance warranty service centre. His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff. These are the Functionality Review (FR) and the Overall Scan (OS). The FR must be performed successfully before the OS is begun. On Friday morning, six repair jobs are completed, awaiting these two inspection activities. Processing times are given in minutes.  Job  FR  OS  A 5030 B 3555 C 2520 D 2035 E 1510 F 1025\begin{array} { | c | c | c | } \hline \text { Job } & \text { FR } & \text { OS } \\\hline \text { A } & 50 & 30 \\\hline \text { B } & 35 & 55 \\\hline \text { C } & 25 & 20 \\\hline \text { D } & 20 & 35 \\\hline \text { E } & 15 & 10 \\\hline \text { F } & 10 & 25 \\\hline\end{array} a. What is the optimal sequence of jobs for the objective of minimizing the total flow time? b. Show your work, and document the sequence. c. Chart the solution to this problem. d. What jobs are being processed at time period 90? e. What is the total flow time of this problem? FROS20406080100120140160180200\begin{array} { | l | l | l | l | l | l | l | l | l | l | l | } \hline \mathrm { FR } & & & & & & & & & & \\\hline \mathrm { OS } & & & & & & & & & & \\\hline & 20 & 40 & 60 & 80 & 100 & 120 & 140 & 160 & 180 & 200 \\\hline\end{array}

Correct Answer

verifed

verified

(a) The optimal sequence is F-D-B-A-C-E....

View Answer

Which critical ratio value implies that a job is already late?


A) more than 100
B) 1
C) less than 1
D) 10
E) 110

Correct Answer

verifed

verified

Which of the following is not an effectiveness criterion for scheduling?


A) minimizing customer waiting time
B) minimizing completion time
C) minimizing WIP inventory
D) maximizing utilization
E) maximizing flow time

Correct Answer

verifed

verified

The jobs listed below needed to be completed. Assume that it is now day 140. If the jobs are sequenced according to shortest processing time rule, what is the average completion time?  Job  Processing  Time (days)   Job due date  (days)   A 20180 B 30200 C 10175 D 16230 E 18210\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (days) }\end{array} & \begin{array} { c } \text { Job due date } \\\text { (days) }\end{array} \\\hline \text { A } & 20 & 180 \\\hline \text { B } & 30 & 200 \\\hline \text { C } & 10 & 175 \\\hline \text { D } & 16 & 230 \\\hline \text { E } & 18 & 210 \\\hline\end{array}


A) 47.6 days
B) 60.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days

Correct Answer

verifed

verified

Identify the disadvantages of the Gantt load chart.

Correct Answer

verifed

verified

It does not account for production varia...

View Answer

Some firms have developed arrangements to literally "swap" employees with each other during their respective peak demand times.

Correct Answer

verifed

verified

Which file contains important information regarding an item's flow through the shop?


A) item master file
B) work-centre master file
C) control files
D) routing file
E) process file

Correct Answer

verifed

verified

Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below. a. What is the optimal sequence? b. What is the total flow time for this sequence?  Job  Machine 1  Machine 2  L 1011 M 817N149O137P108\begin{array} { | c | c | c | } \hline \text { Job } & \text { Machine 1 } & \text { Machine 2 } \\\hline \text { L } & 10 & 11 \\\hline \text { M } & 8 & 17 \\\hline \mathrm { N } & 14 & 9 \\\hline \mathrm { O } & 13 & 7 \\\hline \mathrm { P } & 10 & 8 \\\hline\end{array}

Correct Answer

verifed

verified

(a,b) The optimal sequence is ...

View Answer

Which of the following best describes the strategic importance of short-term scheduling?


A) Effective scheduling, through lower costs, faster delivery, and dependable delivery, can provide a competitive advantage.
B) Effective scheduling is a tactical tool for increasing demand to meet production.
C) Forward scheduling looks to future demand levels in order to increase customer satisfaction.
D) Aggregate planning is a tactical action, but short-term scheduling is strategic because of its immense impact on costs.
E) Short-term scheduling matches capacity to demand during the short term, three to eighteen months into the future.

Correct Answer

verifed

verified

Sequencing (or dispatching)


A) assigns dates to specific jobs or operations steps.
B) assigns jobs to work centres.
C) specifies the order in which jobs should be done at each centre.
D) assigns workers to jobs.
E) assigns workers to machines.

Correct Answer

verifed

verified