Given the following Product Structure Record: Given the following Product Structure Record:   The number of G's required to assemble 10 A's would be A) 9. B) 10. C) 90. D) 180. The number of G's required to assemble 10 A's would be


A) 9.
B) 10.
C) 90.
D) 180.

Correct Answer

verifed

verified

The total length of time to purchase an item from a supplier is called its cumulative lead time.

Correct Answer

verifed

verified

Given the following MRP matrix for Item D: Given the following MRP matrix for Item D:   The planned order release for period 3 would be A) 100. B) 160. C) 270. D) 300. The planned order release for period 3 would be


A) 100.
B) 160.
C) 270.
D) 300.

Correct Answer

verifed

verified

Enterprise resource planning integrates business processes at the expense of customer interaction.

Correct Answer

verifed

verified

Given the following Product Structure Record: Given the following Product Structure Record:   The number of I's required for each A would be A) 1. B) 2. C) 6. D) 12. The number of I's required for each A would be


A) 1.
B) 2.
C) 6.
D) 12.

Correct Answer

verifed

verified

Modular bills of material are used to group small,loose parts together into a kit.

Correct Answer

verifed

verified

The MRP process of subtracting on-hand quantities and scheduled receipts from gross requirements to produce net requirements is referred to as


A) cycle counting.
B) lot sizing.
C) exploding.
D) netting.

Correct Answer

verifed

verified

A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.   If the periodic order quantity lot sizing rule is used,then planned order releases in Period 2 would be A) 40 in period 1. B) 60 in period 2. C) 120 in period 3. D) 140 in Period 2. If the periodic order quantity lot sizing rule is used,then planned order releases in Period 2 would be


A) 40 in period 1.
B) 60 in period 2.
C) 120 in period 3.
D) 140 in Period 2.

Correct Answer

verifed

verified

A ___ of material is used to plan the production of products with many optional features.


A) K-bill
B) modular bill
C) phantom bill
D) time-phased bill

Correct Answer

verifed

verified

Customer relationship management systems change the focus from managing products to managing customers.

Correct Answer

verifed

verified

Capacity requirements planning (CRP)projects the load from a given material plan onto the capacity of a system.

Correct Answer

verifed

verified

One objective of material requirements planning (MRP)is to utilize all available capacity.

Correct Answer

verifed

verified

Given the following Product Structure Record: Given the following Product Structure Record:   The number of E's required for each A would be A) 3. B) 6. C) 12. D) 24. The number of E's required for each A would be


A) 3.
B) 6.
C) 12.
D) 24.

Correct Answer

verifed

verified

All of the following are inputs into the MRP process except


A) the master production schedule.
B) the product structure file.
C) the item master file.
D) the planned order report.

Correct Answer

verifed

verified

Customer relationship management (CRM)software plans and executes business processes that involve customer interactions.

Correct Answer

verifed

verified

The product structure file lists all of the following except


A) the product's demand.
B) the items that go into the product.
C) a brief description of each item.
D) when and in what quantity each item is needed in the assembly process.

Correct Answer

verifed

verified

The master production schedule (MPS)is a major output of the MRP process.

Correct Answer

verifed

verified

Given the following MRP matrix for Item D: Given the following MRP matrix for Item D:   The planned order release for period 5 would be A) 100. B) 120. C) 160. D) 270. The planned order release for period 5 would be


A) 100.
B) 120.
C) 160.
D) 270.

Correct Answer

verifed

verified

Given the following MRP matrix for Item D: Given the following MRP matrix for Item D:   The planned order receipt for period 6 would be A) 100. B) 120. C) 160. D) 270. The planned order receipt for period 6 would be


A) 100.
B) 120.
C) 160.
D) 270.

Correct Answer

verifed

verified

A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.   If L4L ordering is used the planned order releases would be A) 40 in period 1 and 0 in period 3. B) 80 in period 2 and 60 in period 3. C) 60 in period 2 and 80 in period 3. D) 0 in period 1 and 40 in period 3. If L4L ordering is used the planned order releases would be


A) 40 in period 1 and 0 in period 3.
B) 80 in period 2 and 60 in period 3.
C) 60 in period 2 and 80 in period 3.
D) 0 in period 1 and 40 in period 3.

Correct Answer

verifed

verified