Filters
Question type

Study Flashcards

Risk is a measure of the probability and consequences of not reaching a defined project goal.

Correct Answer

verifed

verified

What are the benefits of using CPM/PERT?

Correct Answer

verifed

verified

The benefits are forcing project teams t...

View Answer

Free slack is the amount of time that an activity's earliest finish time can be delayed without delaying the earliest start time of any activity immediately following it.

Correct Answer

verifed

verified

Table 3.5  Activity  Immediate  Predecessor(s)   Time  (weeks)   A 6 B 3 C  A,B 2 D  A 6 E  C 2 F  D,E 2 G  C 8\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 6 \\\text { B } & \cdots & 3 \\\text { C } & \text { A,B } & 2 \\\\\text { D } & \text { A } & 6 \\\text { E } & \text { C } & 2 \\\text { F } & \text { D,E } & 2 \\\text { G } & \text { C } & 8 \\\hline\end{array} -Using Table 3.5,what is the critical path of this project?


A) A-C-G
B) B-C-G
C) A-C-E-F
D) A-D-F

Correct Answer

verifed

verified

Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks) .  Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 2514 B 81114 C 579 A  D 6912 A  E 135 D,B \begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 2 & 5 & 14 & \cdots \\\text { B } & 8 & 11 & 14 & \cdots \\\text { C } & 5 & 7 & 9 & \text { A } \\\text { D } & 6 & 9 & 12 & \text { A } \\\text { E } & 1 & 3 & 5 & \text { D,B } \\\hline\end{array} -Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.


A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%

Correct Answer

verifed

verified

What characteristics should project manager possess?

Correct Answer

verifed

verified

Project managers should be goo...

View Answer

When using the beta distribution for estimating activity times,


A) an advantage is that the mode of the distribution is always equidistant from the end points of the distribution.
B) the most likely time estimate can be positioned anywhere between the optimistic and pessimistic time estimates.
C) we assume that the standard deviation is one-third the range between the optimistic and pessimistic time estimates.
D) the most likely time estimate becomes the mean of the distribution.

Correct Answer

verifed

verified

Table 3.4  Activity  Immediate  Predecessor(s)   Time  (weeks)   A 2 B 2 C 2 D  A 2 E  B 2 F  B 2 G  C 2 H  E 2 I  F 2 J  D 2 K  I 2 L  K,H 2 M  G 2 N  L, J 2\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 2 \\\text { B } & \cdots & 2 \\\text { C } & \cdots & 2 \\\\\text { D } & \text { A } & 2 \\\text { E } & \text { B } & 2 \\\text { F } & \text { B } & 2 \\\\\text { G } & \text { C } & 2 \\\text { H } & \text { E } & 2 \\\text { I } & \text { F } & 2 \\\\\text { J } & \text { D } & 2 \\\text { K } & \text { I } & 2 \\\text { L } & \text { K,H } & 2 \\\\\text { M } & \text { G } & 2 \\\text { N } & \text { L, J } & 2 \\\hline\end{array} -Using Table 3.4,of the following activities,which one has a slack value greater than zero weeks?


A) Activity B
B) Activity C
C) Activity K
D) Activity N

Correct Answer

verifed

verified

Table 3.4  Activity  Immediate  Predecessor(s)   Time  (weeks)   A 2 B 2 C 2 D  A 2 E  B 2 F  B 2 G  C 2 H  E 2 I  F 2 J  D 2 K  I 2 L  K,H 2 M  G 2 N  L, J 2\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 2 \\\text { B } & \cdots & 2 \\\text { C } & \cdots & 2 \\\\\text { D } & \text { A } & 2 \\\text { E } & \text { B } & 2 \\\text { F } & \text { B } & 2 \\\\\text { G } & \text { C } & 2 \\\text { H } & \text { E } & 2 \\\text { I } & \text { F } & 2 \\\\\text { J } & \text { D } & 2 \\\text { K } & \text { I } & 2 \\\text { L } & \text { K,H } & 2 \\\\\text { M } & \text { G } & 2 \\\text { N } & \text { L, J } & 2 \\\hline\end{array} -Using Table 3.4,what is the latest finish time for activity D?


A) 4 weeks
B) 6 weeks
C) 8 weeks
D) 10 weeks

Correct Answer

verifed

verified

Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks) .  Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 2514 B 81114 C 579 A  D 6912 A  E 135 D,B \begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 2 & 5 & 14 & \cdots \\\text { B } & 8 & 11 & 14 & \cdots \\\text { C } & 5 & 7 & 9 & \text { A } \\\text { D } & 6 & 9 & 12 & \text { A } \\\text { E } & 1 & 3 & 5 & \text { D,B } \\\hline\end{array} -Using Table 3.10,what is the probability that the project will take 16 or more weeks to complete? You will need to refer to a standard normal table to answer the question.


A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%

Correct Answer

verifed

verified

The optimistic time is the probable time required to perform the activity.

Correct Answer

verifed

verified

Table 3.3  Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 3 C 3 D  B 4 E  A,C 4 F  B 4 G  H  E 5 I  E 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 3 \\\text { C } & \cdots & 3 \\\text { D } & \text { B } & 4 \\\text { E } & \text { A,C } & 4 \\\text { F } & \text { B } & 4 \\\text { G } & & \\\text { H } & \text { E } & 5 \\\text { I } & \text { E } & 5 \\\hline\end{array} -Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?


A) 1 activity
B) 2 activities
C) 3 activities
D) 4 or more activities

Correct Answer

verifed

verified

Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks) .  Activity  Expected  Time  Immediate  Predecessor (s) A3 B 3 C 5 A  D 4 A,B  E 4 B  F 4 C,D  G 3D,EH5 F,G\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 3 & \cdots - \\\text { B } & 3 & - \\\text { C } & 5 & \text { A } \\\text { D } & 4 & \text { A,B } \\\text { E } & 4 & \text { B } \\\text { F } & 4 & \text { C,D } \\\text { G } & 3 & \mathrm { D } , \mathrm { E } \\\mathrm { H } & 5 & \mathrm {~F} , \mathrm { G } \\\hline\end{array} -Using Table 3.12,which of the following activities has the largest amount of slack?


A) Activity C
B) Activity D
C) Activity E
D) Activity H

Correct Answer

verifed

verified

The activities along the critical path determine the completion time for the project.

Correct Answer

verifed

verified

A critical path is the sequence of activities between a project's start and finish.

Correct Answer

verifed

verified

Projects cannot have more than one critical path.

Correct Answer

verifed

verified

Table 3.2 Time (days)  Activity  Immediate  Predecessor(s)   Most  Optimistic  Most  Likely  Most  Pessimistic  A 246 B 147 C  A 222 D  B 1710 E  D 246 F  E 123 G  C 3417 H  D, G 3711 I  D 8910 J  F,H 456 K  I 111\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Most } \\\text { Optimistic }\end{array} & \begin{array} { c } \text { Most } \\\text { Likely }\end{array} & \begin{array} { c } \text { Most } \\\text { Pessimistic }\end{array} \\\hline \text { A } & \cdots & 2 & 4 & 6 \\\text { B } & \cdots & 1 & 4 & 7 \\\text { C } & \text { A } & 2 & 2 & 2 \\\text { D } & \text { B } & 1 & 7 & 10 \\\text { E } & \text { D } & 2 & 4 & 6 \\\text { F } & \text { E } & 1 & 2 & 3 \\\text { G } & \text { C } & 3 & 4 & 17 \\\text { H } & \text { D, G } & 3 & 7 & 11 \\\text { I } & \text { D } & 8 & 9 & 10 \\\text { J } & \text { F,H } & 4 & 5 & 6 \\\text { K } & \text { I } & 1 & 1 & 1 \\\hline\end{array} -Using Table 3.2,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager? You will need to refer to a standard normal table to answer the question.


A) less than or equal to 28 days
B) greater than 28 days but less than or equal to 30 days
C) greater than 30 days but less than or equal to 32 days
D) greater than 32 days

Correct Answer

verifed

verified

To calculate the probability of completing a project by a certain date,


A) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
B) the variance of the distribution of project completion times is taken to be one-sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
C) we assume that the activity durations are independent of each other so that the normal distribution can be used.
D) we only need the parameters of the beta distribution for the finish node of the diagram.

Correct Answer

verifed

verified

Which one of the following best describes the critical path of a PERT/CPM network?


A) the sequence of activities between a project's start and finish that takes the longest time to complete.
B) the sequence of activities between a project's start and finish that has the maximum amount of activity slack.
C) the set of activities that has no precedence relationships.
D) the sequence of activities that has the lowest normal activity cost.

Correct Answer

verifed

verified

Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks) .  Activity  Expected  Time  Immediate  Predecessor (s) A3 B 3 C 5 A  D 4 A,B  E 4 B  F 4 C,D  G 3D,EH5 F,G\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 3 & \cdots - \\\text { B } & 3 & - \\\text { C } & 5 & \text { A } \\\text { D } & 4 & \text { A,B } \\\text { E } & 4 & \text { B } \\\text { F } & 4 & \text { C,D } \\\text { G } & 3 & \mathrm { D } , \mathrm { E } \\\mathrm { H } & 5 & \mathrm {~F} , \mathrm { G } \\\hline\end{array} -Using Table 3.12,what is the critical path for this network?


A) A-C-F-H
B) A-D-F-H
C) B-D-G-H
D) B-E-G-H

Correct Answer

verifed

verified

Showing 61 - 80 of 153

Related Exams

Show Answer