Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) A-C-G
B) B-C-G
C) A-C-E-F
D) A-D-F
Correct Answer
verified
Multiple Choice
A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) an advantage is that the mode of the distribution is always equidistant from the end points of the distribution.
B) the most likely time estimate can be positioned anywhere between the optimistic and pessimistic time estimates.
C) we assume that the standard deviation is one-third the range between the optimistic and pessimistic time estimates.
D) the most likely time estimate becomes the mean of the distribution.
Correct Answer
verified
Multiple Choice
A) Activity B
B) Activity C
C) Activity K
D) Activity N
Correct Answer
verified
Multiple Choice
A) 4 weeks
B) 6 weeks
C) 8 weeks
D) 10 weeks
Correct Answer
verified
Multiple Choice
A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1 activity
B) 2 activities
C) 3 activities
D) 4 or more activities
Correct Answer
verified
Multiple Choice
A) Activity C
B) Activity D
C) Activity E
D) Activity H
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) less than or equal to 28 days
B) greater than 28 days but less than or equal to 30 days
C) greater than 30 days but less than or equal to 32 days
D) greater than 32 days
Correct Answer
verified
Multiple Choice
A) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
B) the variance of the distribution of project completion times is taken to be one-sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
C) we assume that the activity durations are independent of each other so that the normal distribution can be used.
D) we only need the parameters of the beta distribution for the finish node of the diagram.
Correct Answer
verified
Multiple Choice
A) the sequence of activities between a project's start and finish that takes the longest time to complete.
B) the sequence of activities between a project's start and finish that has the maximum amount of activity slack.
C) the set of activities that has no precedence relationships.
D) the sequence of activities that has the lowest normal activity cost.
Correct Answer
verified
Multiple Choice
A) A-C-F-H
B) A-D-F-H
C) B-D-G-H
D) B-E-G-H
Correct Answer
verified
Showing 61 - 80 of 153
Related Exams