A) Once production begins, it continues until the finished product emerges.
B) The products produced are heterogeneous in nature.
C) The focus is on continually producing similar products.
D) When the finished product emerges, all units have exactly the same amount of materials, labour, and overhead.
Correct Answer
verified
Multiple Choice
A) 8,400 equivalent units
B) 14,000 equivalent units
C) 10,000 equivalent units
D) 4,000 equivalent units
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) There is a separate Work in Process account for each process.
B) A subsidiary ledger tracks the costs of each job.
C) There is a separate Work in Process account for each product.
D) Materials are added at the beginning process, and conversion costs are added at the end.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 36,000 units
B) 32,000 units
C) 21,000 units
D) 30,000 units
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Job order cost sheet
B) Process order cost sheet
C) Production cost report
D) Manufacturing cost sheet
Correct Answer
verified
Multiple Choice
A) 42,000 equivalent units
B) 28,500 equivalent units
C) 37,500 equivalent units
D) 38,000 equivalent units
Correct Answer
verified
Multiple Choice
A) They are debited to Finished Goods Inventory.
B) They are transferred to Cost of Goods Sold.
C) They are debited to Work in Process-Department 23.
D) They are credited to Manufacturing Overhead.
Correct Answer
verified
Multiple Choice
A) Finished Goods Inventory account was increased.
B) Cost of Goods Sold was increased.
C) A Manufacturing Overhead account was reduced.
D) The Work in Process account was reduced.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) In process cost systems, costs are accumulated and assigned.
B) A process cost system has one work in process account for each job.
C) In process cost systems, costs are summarized by batch.
D) Unit costs are ignored in process cost systems because they are identical.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 65