Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV) , then compounding this PV to find the IRR.
B) If a project's IRR is greater than the WACC, then its NPV must be negative.
C) To find a project's IRR, we must solve for the discount rate that causes the PV of the inflows to equal the PV of the project's costs.
D) To find a project's IRR, we must find a discount rate that is equal to the WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method is that it does not take account of cash flows over a project's full life.
B) One defect of the IRR method is that it does not take account of the time value of money.
C) One defect of the IRR method is that it does not take account of the cost of capital.
D) One defect of the IRR method is that it assumes that the cash flows to be received from a project can be reinvested at the IRR itself, and that assumption is often not valid.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) More of Project A's cash flows occur in the later years.
B) More of Project B's cash flows occur in the later years.
C) We must have information on the cost of capital in order to determine which project has the larger early cash flows.
D) The NPV profile graph is inconsistent with the statement made in the problem.
Correct Answer
verified
Multiple Choice
A) 9.56%
B) 10.33%
C) 11.21%
D) 12.55%
Correct Answer
verified
Multiple Choice
A) 14.04%
B) 15.44%
C) 16.99%
D) 18.69%
Correct Answer
verified
Multiple Choice
A) A,$71,687
B) A,$16,702
C) B,$23,954
D) B,$9,718
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
Correct Answer
verified
Multiple Choice
A) $243.43
B) $255.60
C) $268.38
D) $281.80
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal value to equal the initial cost.
D) To find a project's MIRR, the textbook procedure compounds cash inflows at the WACC and then finds the discount rate that causes the PV of the terminal value to equal the initial cost.
Correct Answer
verified
Multiple Choice
A) 1.72 years
B) 1.92 years
C) 2.13 years
D) 2.36 years
Correct Answer
verified
Multiple Choice
A) payback = 2.4, IRR = 10.00%, NPV = $600
B) payback = 2.4, IRR = 21.22%, NPV = $260
C) payback = 2.6, IRR = 21.22%, NPV = $300
D) payback = 2.6, IRR = 21.22%, NPV = $260
Correct Answer
verified
Multiple Choice
A) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the NPV method provides.
B) The discounted payback method eliminates all of the problems associated with the payback method.
C) When evaluating independent projects, the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
D) To find the MIRR, we discount the TV at the IRR.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $253.81
B) $282.01
C) $310.21
D) $341.23
Correct Answer
verified
True/False
Correct Answer
verified
Showing 41 - 60 of 108
Related Exams