Filters
Question type

Study Flashcards

A process cost accounting system is most appropriate when


A) a variety of different products are produced each one requiring different types of materials labor and overhead.
B) the focus of attention is on a particular job or order.
C) similar products are mass-produced.
D) individual products are custom made to the specification of customers.

Correct Answer

verifed

verified

A product requires processing in two departments the Baking Department and then the Packaging Department before it is completed. Costs transferred out of the Baking Department will be transferred to:


A) Finished Goods Inventory.
B) Cost of Goods Sold.
C) Work in Process-Packaging Department.
D) Manufacturing Overhead.

Correct Answer

verifed

verified

The following department data are available:  Total materials costs $180,000 Equivalent units of materials 60,000 Total conversion costs $105,000 Equivalent units of conversion costs 30,000\begin{array}{lr}\text { Total materials costs } & \$ 180,000 \\\text { Equivalent units of materials } & 60,000 \\\text { Total conversion costs } & \$ 105,000 \\\text { Equivalent units of conversion costs } & 30,000\end{array} What is the total manufacturing cost per unit?


A) $3.00.
B) $3.50.
C) $6.50.
D) $4.75.

Correct Answer

verifed

verified

Honrad Company's Assembly Department has materials cost at $4 per unit and conversion cost at $8 per unit. There are 30000 units in ending work in process all of which are 70% complete as to conversion costs. Materials are added at the beginning of the process. How much are total costs to be assigned to inventory?


A) $168000.
B) $288000.
C) $253200.
D) $360000.

Correct Answer

verifed

verified

In the production cost report the total


A) physical units accounted for equals the costs accounted for.
B) physical units accounted for equals the units to be accounted for.
C) costs charged equals the units to be accounted for.
D) costs accounted for equals the costs of the units started into production.

Correct Answer

verifed

verified

A process began the month with 3000 units in the beginning work in process inventory and ended the month with 2000 units in the ending work in process. If 22000 units were completed and transferred out of the process during the month how many units were started into production during the month?


A) 21000.
B) 23000.
C) 22000.
D) 20000.

Correct Answer

verifed

verified

Activity-based costing (ABC) can be used only with process cost systems.

Correct Answer

verifed

verified

Process cost systems are used to apply costs to similar products that are ____________ in a ____________ fashion.

Correct Answer

verifed

verified

mass-produ...

View Answer

A department adds raw materials to a process at the beginning of the process and incurs conversion costs uniformly throughout the process. For the month of January there were no units in the beginning work in process inventory; 90000 units were started into production in January; and there were 20000 units that were 40% complete in the ending work in process inventory at the end of January. What were the equivalent units of production for materials for the month of January?


A) 98000 equivalent units.
B) 82000 equivalent units.
C) 70000 equivalent units.
D) 90000 equivalent units.

Correct Answer

verifed

verified

Price Company assigns overhead based on machine hours. The Milling Department logs 2400 machine hours and Cutting Department shows 4000 machine hours for the period. If the overhead rate is $5 per machine hour the entry to assign overhead will show a


A) debit to Manufacturing Overhead for $32000.
B) credit to Work in Process-Cutting Department for $20000.
C) debit to Work in Process for $20000.
D) credit to Manufacturing Overhead for $32000.

Correct Answer

verifed

verified

Gantner Company had the following department information about physical units and percentage of completion:  Physical Units  Work in process, May 1(60%) 60,000 Completed and transferred out 180,000 Work in process, May 31(40%) 50,000\begin{array} { l r } & \text { Physical Units } \\\text { Work in process, May } 1 ( 60 \% ) & 60,000 \\\text { Completed and transferred out } & 180,000 \\\text { Work in process, May } 31 ( 40 \% ) &50,000\end{array} If materials are added at the beginning of the production process what is the total number of equivalent units for materials during May?


A) 240000.
B) 230000.
C) 224000.
D) 200000.

Correct Answer

verifed

verified

The Kirkland Department of Delta Company began the month of December with beginning work in process of 4000 units that are 100% complete as to materials and 30% complete as to conversion costs. Units transferred out are 10000 units. Ending work in process contains 8000 units that are 100% complete as to materials and 60% complete as to conversion costs. Instructions Compute the equivalent units of production for materials and conversion costs for the month of December.

Correct Answer

verifed

verified

In a process cost system


A) a Work in Process account is maintained for each product.
B) a materials requisition must identify the job on which the materials will be used.
C) a Work in Process account is maintained for each process.
D) one Work in Process account is maintained for all the processes similar to a job order cost system.

Correct Answer

verifed

verified

Materials costs of $1200000 and conversion costs of $1530000 were charged to a processing department in the month of September. Materials are added at the beginning of the process while conversion costs are incurred uniformly throughout the process. There were no units in beginning work in process 20000 units were started into production in September and there were 5000 units in ending work in process that were 40% complete at the end of September. What was the total amount of manufacturing costs assigned to those units that were completed and transferred out of the process in September?


A) $2250000.
B) $3000000.
C) $2409750.
D) $2047500.

Correct Answer

verifed

verified

In the Shaping Department of Rollins Company the unit materials cost is $5.00 and the unit conversion cost is $3.00. The department transferred out 40000 units and had 5000 units in ending work in process 20% complete. If all materials are added at the beginning of the process the total cost to be assigned to the ending work in process is


A) $8000.
B) $25000.
C) $28000.
D) $40000.

Correct Answer

verifed

verified

The flow of costs in a process costing system requires that materials be added in one department labor added in another department and manufacturing overhead in a third department.

Correct Answer

verifed

verified

The Molding Department of Boswell Company has the following production data: beginning work process 40000 units (60% complete) started into production 730000 units completed and transferred out 690000 units and ending work in process 80000 units (40% complete) . Assuming materials are entered at the beginning of the process equivalent units for materials are:


A) 770000.
B) 650000.
C) 690000.
D) 810000.

Correct Answer

verifed

verified

Long Company has recently tried to improve its analysis for its manufacturing process. Units started into production equaled 6000 and ending work in process equaled 400 units. Long had no beginning work in process inventory. Conversion costs are applied equally throughout production and materials are applied at the beginning of the process. How much is the materials cost per unit if ending work in process was 25% complete and total materials costs equaled $18000?


A) $3.00.
B) $3.16.
C) $11.25.
D) $2.81.

Correct Answer

verifed

verified

Grey Building Supplies' total materials costs are $30000 and total conversion costs are $33000. Equivalent units of production for materials are 10000 and 5000 for conversion costs. Instructions Compute the unit costs for materials conversion costs and total manufacturing costs for the month.

Correct Answer

verifed

verified

None...

View Answer

An important assumption in using ABC is that


A) production must take place on a continuous basis.
B) all costs in an activity should respond proportionately to changes in the activity level of the cost driver.
C) production must take place on a just-in-time basis.
D) all costs are pushed through each process when customer orders are received.

Correct Answer

verifed

verified

Showing 121 - 140 of 195

Related Exams

Show Answer