Pepper Industries uses a standard cost accounting system. During March, 2016, the company reported the following manufacturing variances: Pepper Industries uses a standard cost accounting system. During March, 2016, the company reported the following manufacturing variances:    In addition, 15,000 units of product were sold at $18 per unit. Each unit sold had a standard cost of $14. Selling and administrative expenses for the month were $15,000. Instructions Prepare an income statement for management for the month ending March 31, 2016. In addition, 15,000 units of product were sold at $18 per unit. Each unit sold had a standard cost of $14. Selling and administrative expenses for the month were $15,000. Instructions Prepare an income statement for management for the month ending March 31, 2016.

Correct Answer

verifed

verified

The difference between a budget and a standard is that


A) a budget expresses what costs were, while a standard expresses what costs should be.
B) a budget expresses management's plans, while a standard reflects what actually happened.
C) a budget expresses a total amount, while a standard expresses a unit amount.
D) standards are excluded from the cost accounting system, whereas budgets are generally incorporated into the cost accounting system.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

The cost of freight-in


A) is to be included in the standard cost of direct materials.
B) is considered a selling expense.
C) should have a separate standard apart from direct materials.
D) should not be included in a standard cost system.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The standard direct labor cost for producing one unit of product is 5 direct labor hours at a standard rate of pay of $20. Last month, 15,000 units were produced and 73,500 direct labor hours were actually worked at a total cost of $1,350,000. The direct labor quantity variance was


A) $30,000 unfavorable.
B) $45,000 unfavorable.
C) $45,000 favorable.
D) $30,000 favorable.

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

Normal standards should be rigorous but attainable.

A) True
B) False

Correct Answer

verifed

verified

The standard unit cost is used in the calculation of which of the following variances? The standard unit cost is used in the calculation of which of the following variances?

Correct Answer

verifed

verified

In using variance reports, top management normally looks carefully at every variance.

A) True
B) False

Correct Answer

verifed

verified

Standard cost is the industry average cost for a particular item.

A) True
B) False

Correct Answer

verifed

verified

In October, Glazier Inc. reports 42,000 actual direct labor hours, and it incurs $194,000 of manufacturing overhead costs. Standard hours allowed for the work done is 40,000 hours. Glazier's predetermined overhead rate is $5.00 per direct labor hour. Instructions Compute the total manufacturing overhead variance.

Correct Answer

verifed

verified

The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 2,400 units, the actual direct labor cost was $46,000 for 3,000 direct labor hours worked, the total direct labor variance is


A) $2,400 unfavorable.
B) $8,000 favorable.
C) $5,000 unfavorable.
D) $8,000 unfavorable.

E) A) and C)
F) A) and D)

Correct Answer

verifed

verified

The difference between actual quantity of materials times the standard price and standard quantity times the standard price is the materials ________________ variance.

Correct Answer

verifed

verified

A standard cost is


A) a cost which is paid for a group of similar products.
B) the average cost in an industry.
C) a predetermined cost.
D) the historical cost of producing a product last year.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Caroline, Inc. planned to produce 20,000 units of product and work 100,000 direct labor hours in 2016. Manufacturing overhead at the 100,000 direct labor hours level of activity was estimated to be: Caroline, Inc. planned to produce 20,000 units of product and work 100,000 direct labor hours in 2016. Manufacturing overhead at the 100,000 direct labor hours level of activity was estimated to be:    At the end of 2016, 19,000 units of product were actually produced and 98,000 actual direct labor hours were worked. Total actual overhead costs for 2016 were $935,000. Instructions (a) Compute the total overhead variance. (b) Compute the overhead controllable variance. (c) Compute the overhead volume variance. At the end of 2016, 19,000 units of product were actually produced and 98,000 actual direct labor hours were worked. Total actual overhead costs for 2016 were $935,000. Instructions (a) Compute the total overhead variance. (b) Compute the overhead controllable variance. (c) Compute the overhead volume variance.

Correct Answer

verifed

verified

Dillon has a standard of 1.5 pounds of materials per unit, at $6 per pound. In producing 2,000 units, Dillon used 3,100 pounds of materials at a total cost of $18,135. Dillon's materials quantity variance is


A) $135 F.
B) $465 U.
C) $600 U.
D) $1,050 U.

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

The perspectives included in the balanced scorecard approach include all of the following except the


A) internal process perspective.
B) capacity utilization perspective.
C) learning and growth perspective.
D) customer perspective.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The formula for the labor price variance is


A) (AH) x (SR) less (SH) x (SR) .
B) (AH) x (AR) less (AH) x (SR) .
C) (AH) x (AR) less (SH) x (SR) .
D) (AH) x (SR) less (AH) x (SR) .

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

In Zero Company's income statement, they report gross profit of $55,000 at standard and the following variances: Materials price $ 420 F Materials quantity 600 F Labor price 420 U Labor quantity 1,000 F Overhead 900 F Zero would report actual gross profit of


A) $51,660.
B) $52,500.
C) $57,500.
D) $58,340.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The following direct materials data pertain to the operations of Wright Co. for the month of December. Standard materials price $5.00 per pound Actual quantity of materials purchased and used 16,500 pounds The standard cost card shows that a finished product contains 4 pounds of materials. The 16,500 pounds were purchased in December at a discount of 4% from the standard price. In December, 4,000 units of finished product were manufactured. Instructions Prepare a matrix for materials and calculate the materials variances. The following direct materials data pertain to the operations of Wright Co. for the month of December. Standard materials price $5.00 per pound Actual quantity of materials purchased and used 16,500 pounds The standard cost card shows that a finished product contains 4 pounds of materials. The 16,500 pounds were purchased in December at a discount of 4% from the standard price. In December, 4,000 units of finished product were manufactured. Instructions Prepare a matrix for materials and calculate the materials variances.

Correct Answer

verifed

verified

Dillon has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2,000 units, Dillon used 3,850 hours of labor at a total cost of $46,970. Dillon's total labor variance is


A) $1,030 U.
B) $800 U.
C) $1,030 F.
D) $1,930 F.

E) None of the above
F) All of the above

Correct Answer

verifed

verified

A variance is the difference between actual costs and standard costs.

A) True
B) False

Correct Answer

verifed

verified