Filters
Question type

Study Flashcards

Most changes on a project are related to


A) scope changes.
B) improvement changes.
C) implementing contingency plans.
D) customer-driven changes to requirements.
E) All of these alternatives are correct.

Correct Answer

verifed

verified

Which of the following risks are likely to be retained?


A) Risks of high consequence
B) Risks of low likelihood
C) Risks of high likelihood
D) Risks that are escalated
E) Risks that are transferred

Correct Answer

verifed

verified

What is the risk value of a risk whose impact score is 5, whose probability score is 5 and whose detection score is 1?


A) 5
B) 25
C) 125
D) 11
E) 10

Correct Answer

verifed

verified

The likelihood of a risk occurring _____ as a project goes through its life cycle.


A) increases
B) decreases
C) moderates
D) amplifies
E) becomes more probable

Correct Answer

verifed

verified

Contingency reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.

Correct Answer

verifed

verified

The risk assessment form contains all of the following EXCEPT


A) likelihood of the risk event occurring.
B) potential impact of the risk event.
C) who will detect the occurrence of the risk event.
D) difficulty of detecting the occurrence of the risk event.
E) when the risk event may occur.

Correct Answer

verifed

verified

The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as


A) risk forecasting.
B) risk management.
C) contingency planning.
D) scenario analysis.
E) disaster protection.

Correct Answer

verifed

verified

Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages.

Correct Answer

verifed

verified

Having an environment where identified risks are treated professionally will lead to better control of risks.

Correct Answer

verifed

verified

What is the difference between contingency reserves and management reserves?

Correct Answer

verifed

verified

Contingency reserves are controlled by t...

View Answer

Adopting proven technology instead of experimental technology is an example of mitigating a risk.

Correct Answer

verifed

verified

Flooding would be devastating to the project; however, it is very unlikely. The project manager is most likely to __________ this risk.


A) prepare for
B) retain
C) diminish
D) distribute
E) acknowledge

Correct Answer

verifed

verified

Choosing to move a concert indoors to eliminate the threat of bad weather is an example of ____________ a risk.


A) transferring
B) escalating
C) avoiding
D) mitigating
E) retaining

Correct Answer

verifed

verified

The project being delayed is an example of a major risk that should be assessed.

Correct Answer

verifed

verified

The cost impact of a risk event occurring as a project proceeds through its life cycle tends to


A) rise sharply.
B) drop sharply and then level out.
C) rise sharply and then level out.
D) remain about the same.
E) slowly drop.

Correct Answer

verifed

verified

Which of the following is NOT one of the potential responses to a specific risk event?


A) Mitigating
B) Retaining
C) Ignoring
D) Transferring
E) Avoiding

Correct Answer

verifed

verified

Risks are evaluated in terms of


A) likelihood and cost.
B) cost and schedule.
C) impact and cost.
D) time and impact.
E) likelihood and impact.

Correct Answer

verifed

verified

Identify and briefly describe the four steps in the risk management process.

Correct Answer

verifed

verified

Risk Response Control-the actu...

View Answer

One common mistake made early in the risk identification process is to


A) not consider all possibilities.
B) encourage participants be over optimistic.
C) support participants being over pessimistic.
D) focus on consequences and not on the events that could produce consequences.
E) give too much attention to past events.

Correct Answer

verifed

verified

Which of the following is NOT included in a Failure Mode and Effects Analysis?


A) Impact
B) Probability
C) Detection
D) Risk value
E) All of these are included

Correct Answer

verifed

verified

Showing 41 - 60 of 105

Related Exams

Show Answer