Filters
Question type

Study Flashcards

In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the


A) mean time.
B) median time.
C) most likely time.
D) mode time.
E) marginal time.

Correct Answer

verifed

verified

Most likely time generally is at least as long as optimistic time.

Correct Answer

verifed

verified

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is


A) 7.0.
B) 7.5.
C) 8.0.
D) 8.5.
E) 10.0.

Correct Answer

verifed

verified

Activities not on the critical path have a slack time equal to zero.

Correct Answer

verifed

verified

Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?


A) expected project duration
B) activity slack time
C) which activities are on the critical path
D) variance in project duration
E) maximum project duration

Correct Answer

verifed

verified

A popular visual tool for planning and scheduling simple projects, and for monitoring progress, is the


A) activity-on-arrows network.
B) activity-on-nodes network.
C) Gantt chart.
D) critical path method.
E) program evaluation and review technique.

Correct Answer

verifed

verified

A method used for establishing a logical framework for identifying the required activities for the project is called


A) work breakdown structure.
B) PERT.
C) planning matrix.
D) crashing.
E) critical path analysis.

Correct Answer

verifed

verified

Slack time is equal to LS-ES or LF-EF.

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity E? A) 35 days B) 36 days C) 39 days D) 40 days E) 45 days What is the estimated expected (mean) time for activity E?


A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days

Correct Answer

verifed

verified

Which of the following is not a limitation of PERT and similar project-scheduling techniques?


A) They force the manager to organize and quantify information.
B) One or more important activities may be omitted from the network.
C) Precedence relationships may not all be correct as shown.
D) Time estimates may contain a "fudge factor."
E) The use of a computer is essential for large projects.

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for project completion? A) 41 days B) 70 days C) 100 days D) 120 days E) 221 days What is the estimated expected (mean) time for project completion?


A) 41 days
B) 70 days
C) 100 days
D) 120 days
E) 221 days

Correct Answer

verifed

verified

Project management software eliminates constraint violations when there are shared resources.

Correct Answer

verifed

verified

One way that project management differs from management of more traditional activities is because of the limited time framework of projects.

Correct Answer

verifed

verified

Activity J has a duration of 7 and an earliest finish time of 21. If J's latest start time is 16, this must mean that J's slack is


A) 7.
B) 4.
C) 3.
D) 2.
E) 1.

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: A) a-c-g. B) a-d-f-g. C) a-d-h-i. D) b-e-f-g. E) b-e-h-i. The critical path for the network shown is:


A) a-c-g.
B) a-d-f-g.
C) a-d-h-i.
D) b-e-f-g.
E) b-e-h-i.

Correct Answer

verifed

verified

Although PERT and CPM were originally developed independently, they are now nearly identical in terms of analysis and procedures.

Correct Answer

verifed

verified

In a project network, the critical path is the sequence of activities which has the


A) most activities.
B) most nodes.
C) most events.
D) longest duration.
E) greatest variance.

Correct Answer

verifed

verified

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity D? A) 0 day B) 30 days C) 40 days D) 50 days E) 100 days What is the estimated slack time for activity D?


A) 0 day
B) 30 days
C) 40 days
D) 50 days
E) 100 days

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for project completion? A) 135 days B) 145 days C) 170 days D) 180 days E) 255 days What is the estimated expected (mean) time for project completion?


A) 135 days
B) 145 days
C) 170 days
D) 180 days
E) 255 days

Correct Answer

verifed

verified

Showing 21 - 40 of 118

Related Exams

Show Answer