Which of the following is NOT one of the activities of the second core process to plan and monitor the project.


A) Establish the work environment"
B) Build work schedules"
C) Evaluate work processes"
D) Estimate the project length"

Correct Answer

verifed

verified

Usually the highest cost for the development and deployment of a new system is _____.


A) License fees for new software"
B) Salaries of the development team"
C) Computer and network equipment"
D) Data center costs"

Correct Answer

verifed

verified

One of the responsibilities of the project manager in getting a project approved is to try to predict the value of business benefits.

Correct Answer

verifed

verified

The sequence of tasks in a schedule that cannot be delayed without delaying the project is called the _______ .

Correct Answer

verifed

verified

In 2009 almost over two-thirds of all software development projects had serious problems with delivering satisfactory results on time.

Correct Answer

verifed

verified

The level of formality of a project is often referred to as _______ .

Correct Answer

verifed

verified

List the three steps required to develop a detailed schedule of the work to be done within an iteration.

Correct Answer

verifed

verified

1.Develop a work breakdown str...

View Answer

Which two of the following questions (decision points) are important when monitoring project progress?


A) Is the task on target?"
B) Is the task too large?"
C) Is the task clearly defined?"
D) Is the variance significant?"
E) Is the corrective action sufficient?"
F) Is the status complete?

Correct Answer

verifed

verified

Which two of the following activities belong to the second core process of planning and monitoring the project?


A) Establish the project environment"
B) Estimate the project cost"
C) Analyze project risk and feasibility"
D) Determine project scope"
E) Estimate the project length"
F) Staff and allocate resources

Correct Answer

verifed

verified

A,F

Agile project managers do not try to answer the question "How much will the project cost?"

Correct Answer

verifed

verified

Since the Agile philosophy embraces change,project scope management is not important for Agile projects.

Correct Answer

verifed

verified

False

With Agile Time Management scheduling is only done on a micro level and not a macro level.

Correct Answer

verifed

verified

True

Which of the following principles of project management identifies all stakeholders?


A) Risk Management"
B) Communications Management"
C) Human Resource Management"
D) Time Management"

Correct Answer

verifed

verified

One important step in estimating the time required for a project is to try to identify all of the functional requirements of a the new system.

Correct Answer

verifed

verified

List several (at least four)of the internal responsibilities of a project manager.

Correct Answer

verifed

verified

1.Develop the project schedule...

View Answer

The present value of $200,000 development costs in year 0 assuming a 10% discount rate is:


A) $180,000"
B) $190,000"
C) $200,000"
D) $210,000"

Correct Answer

verifed

verified

The _______ consists of clients and key manager who review the progress and direct the project.

Correct Answer

verifed

verified

The creation of a work breakdown structure is helpful in the development of what?


A) Software testing plan."
B) Project iteration schedule."
C) Detailed work schedule."
D) Detailed effort estimates of work tasks."

Correct Answer

verifed

verified

List four primary areas that are considered in risk and feasibility analysis.

Correct Answer

verifed

verified

1.Organizational risk and feas...

View Answer

List the four activities of the first core process: Identify the problem and obtain approval.

Correct Answer

verifed

verified

1.Identify the problem
2.Quant...