Filters
Question type

Study Flashcards

The measurement of how easy it would be to detect that the event was going to occur in time to take mitigating action is known as __________.

Correct Answer

verifed

verified

detection difficulty
Explanation: Detect...

View Answer

A key distinction between a risk response and a contingency plan is


A) A risk response is established only for moderate risks while contingency plans are established for major risks.
B) A risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.
C) A risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning.
D) A risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E) A risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.

Correct Answer

verifed

verified

Risks that can result in a system or process that will not work are known as


A) Technical risks.
B) Funding risks.
C) Schedule risks.
D) Cost risks.
E) Unnecessary risks.

Correct Answer

verifed

verified

The cost impact of a risk event occurring as a project proceeds through its life cycle tends to


A) Slowly rise.
B) Drop sharply and then level out.
C) Rise sharply and then level out.
D) Remain about the same.
E) Slowly drop.

Correct Answer

verifed

verified

Which of the following is NOT included in a Failure Mode and Effects Analysis?


A) Impact
B) Probability
C) Detection
D) Risk value
E) All of these are included.

Correct Answer

verifed

verified

_______________ focuses on how to respond to events that have a positive impact on a project.


A) Risk management
B) Opportunity management
C) Value management
D) Contingency management
E) Prospect management

Correct Answer

verifed

verified

The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as


A) Risk forecasting.
B) Risk management.
C) Contingency planning.
D) Scenario analysis.
E) Disaster protection.

Correct Answer

verifed

verified

While a "can do" attitude is essential during implementation, project managers have to encourage critical thinking when it comes to risk identification.

Correct Answer

verifed

verified

Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves.


A) Management
B) Budget
C) Contingency
D) Padded
E) Just in case

Correct Answer

verifed

verified

The risk identification process should be limited to just the core project team.

Correct Answer

verifed

verified

Why might an organization be opposed to developing and implementing a thorough risk management process?

Correct Answer

verifed

verified

Managing risk takes time and money, whic...

View Answer

The project being delayed is an example of a major risk that should be assessed.

Correct Answer

verifed

verified

Which of the following is identified to cover major unforeseen risks and, hence, are applied to the total project?


A) Project reserves
B) Management reserves
C) Time buffers
D) Activity reserves
E) Budget reserves

Correct Answer

verifed

verified

What is Change Control Management and what function does it perform?

Correct Answer

verifed

verified

Change Control Management is the formal ...

View Answer

Tools such as a risk assessment form and a risk severity matrix are used to


A) Identify risks.
B) Control risks.
C) Assess risks.
D) Regulate risks.
E) Respond to risks.

Correct Answer

verifed

verified

Give a real life example of mitigating a risk, avoiding a risk, transferring a risk and retaining a risk.

Correct Answer

verifed

verified

Mitigating a risk: duplicate systems, ba...

View Answer

When considering risk value, the lower the value, the higher the level of risk.

Correct Answer

verifed

verified

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is known as a __________.

Correct Answer

verifed

verified

risk
Explanation: In the context of proj...

View Answer

Including the change control system within the ________ is a key to a successful project.


A) Work Breakdown Structure
B) Project Baseline
C) Risk Management Plan
D) Work Breakdown Structure and Project Baseline

Correct Answer

verifed

verified

When considering risk response development, reducing the likelihood that an event will occur and/or reducing the impact that an adverse event would have on a project is known as _________ the risk.

Correct Answer

verifed

verified

mitigating
Explanation: Reducing risk is...

View Answer

Showing 41 - 60 of 98

Related Exams

Show Answer