A) mean time.
B) median time.
C) most likely timE.
D) mode time.
E) marginal time.
Correct Answer
verified
Multiple Choice
A) 0 days
B) 2 days
C) 3 days
D) 4 days
E) 12 days
Correct Answer
verified
Multiple Choice
A) 18
B) 17
C) 13
D) 12
E) 10
Correct Answer
verified
Multiple Choice
A) 0 days
B) 25 days
C) 35 days
D) 45 days
E) 85 days
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 0 days
B) 30 days
C) 40 days
D) 50 days
E) 100 days
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) I
B) II
C) III
D) IV
E) V
Correct Answer
verified
Multiple Choice
A) 13.
B) 15.
C) 20.
D) 52.
E) 81.
Correct Answer
verified
Multiple Choice
A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1 days
B) 2 days
C) 3 days
D) 4 days
E) 5 days
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) its ability to reveal relationships among activities.
B) its difficulty in depicting networks.
C) its complexity.
D) its simplicity.
E) its lack of riskiness.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 3.
B) 5.
C) 9.
D) 16.
E) 25.
Correct Answer
verified
Multiple Choice
A) 1-3-6-7.
B) 1-2-4-7.
C) 1-4-7.
D) 1-3-4-7.
E) 1-2-5-7.
Correct Answer
verified
Multiple Choice
A) 7.0.
B) 7.5.
C) 8.0.
D) 8.5.
E) 10.0.
Correct Answer
verified
Multiple Choice
A) These are two different names for essentially the same techniquE.
B) CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) CPM is useful for project manager selection; PERT is useful for project team selection.
Correct Answer
verified
Multiple Choice
A) when the project is completed
B) when no additional crashing is possible
C) when the cost to crash equals or exceeds the benefit of crashing
D) when the project is one-half completed
E) when the team has been disbanded
Correct Answer
verified
Showing 41 - 60 of 113
Related Exams