What is the estimated standard deviation (in weeks) for the critical path completion time?

Correct Answer

verifed

verified

The expected duration of this project is:


A) 13
B) 15
C) 20
D) 52
E) 81

Correct Answer

verifed

verified

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days.The standard deviation of the critical path is:


A) 3
B) 5
C) 9
D) 16
E) 25

Correct Answer

verifed

verified

The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.

Correct Answer

verifed

verified

In crashing this project to 18 weeks, which activities (in order of selection) will be reduced? A.

Correct Answer

verifed

verified

The task of identifying risks should involve everyone associated with the project.

Correct Answer

verifed

verified

The total cost of crashing any one activity should never exceed 20% of the total cost of the original project.

Correct Answer

verifed

verified

Most likely time generally is more than optimistic time.

Correct Answer

verifed

verified

Slack time is equal to LS-ES or LF-EF.

Correct Answer

verifed

verified

The critical path for the network shown is:


A) 1-3-6-7
B) 1-2-4-7
C) 1-4-7
D) 1-3-4-7
E) 1-2-5-7

Correct Answer

verifed

verified

If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.

Correct Answer

verifed

verified

In a project network the critical path is the sequence of activities which has the:


A) most activities
B) most nodes
C) most events
D) longest time
E) greatest variance

Correct Answer

verifed

verified

Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is:


A) 0
B) 1
C) 5
D) 6
E) 11

Correct Answer

verifed

verified

In PERT, the path with the fewest activities is referred to as the critical path.

Correct Answer

verifed

verified

If an activity is determined to be on the critical, that means that it, and perhaps other, will affect project ____________.


A) direct costs
B) performance
C) quality
D) conflict
E) duration

Correct Answer

verifed

verified

Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17.Its slack is:


A) 0
B) 1
C) 4
D) 5
E) 9

Correct Answer

verifed

verified

What is the estimated slack time for activity W?


A) 0 days
B) 25 days
C) 35 days
D) 45 days
E) 85 days

Correct Answer

verifed

verified

What is the estimated standard deviation in the time for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

Correct Answer

verifed

verified

To _____ an activity means to shorten the time it will take.


A) Speed
B) Fund
C) Crash
D) Aggregate
E) Matrix

Correct Answer

verifed

verified

What is the estimated standard deviation in the time for activity D?


A) 0 days
B) 2 days
C) 3 days
D) 4 days
E) 12 days

Correct Answer

verifed

verified