The most widely used approach to apply heuristics, which have been found to consistently minimize project delay over a large variety of projects is the


A) Parallel method
B) Resource method
C) Materials
D) Both A and C are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

A special truck that George needs on his project has been scheduled on another project.This is a ______ constraint.


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

Correct Answer

verifed

verified

In scheduling terms, ________ constrained means that project duration is fixed and resources are flexible.

Correct Answer

verifed

verified

time Explanation: In scheduling terms, time constrained means time (project duration) is fixed and resources are flexible.

Start-up and shutdown costs are major considerations when using the ________________ scheduling technique.

Correct Answer

verifed

verified

splitting/multitasking
Explana...

View Answer

The sequence of (1) pour foundation, (2) build frame, and (3) cover roof is a type of physical constraint.

Correct Answer

verifed

verified

Scheduling resource-constrained projects focuses on completing the project as soon as possible under the given constraints.

Correct Answer

verifed

verified

True

Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization with a low level of risk.She should move to activities with the


A) Smallest duration
B) Least slack
C) Most slack
D) Lowest identification number
E) Highest cost

Correct Answer

verifed

verified

Having one person responsible for performing several activities, all due at the same time, is an example of a(n) ________ constraint.

Correct Answer

verifed

verified

resource
Explanation: If one p...

View Answer

A project that is not resource-constrained is time-constrained.

Correct Answer

verifed

verified

What are the three most common heuristics (in order of priority) used to allocate resources to project activities?

Correct Answer

verifed

verified

1.minimum slack; start with activities w...

View Answer

Sam is trying to order the concrete needed to continue his project.However, the supplier won't be able to deliver it until next week.This is an example of a _______ constraint.


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

Correct Answer

verifed

verified

When developing a new software package, the software must be designed, the code must be written, and the code must be tested.This is an example of a ______ constraint.


A) Physical
B) Technical
C) Resource
D) Schedule
E) Time

Correct Answer

verifed

verified

B

What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?

Correct Answer

verifed

verified

In time-constrained projects the goal is...

View Answer

Identify and briefly describe the three types of project constraints.

Correct Answer

verifed

verified

1.Technical (logic); the sequence that a...

View Answer

All of the following are kinds of resource constraints except


A) Materials
B) People
C) Equipment
D) Information
E) All of the above are resource constraints

Correct Answer

verifed

verified

Identify and briefly describe the potential impacts of resource-constrained scheduling.

Correct Answer

verifed

verified

1.reduced slack reduces flexibility, 2.i...

View Answer

Resource Bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.

Correct Answer

verifed

verified

Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.


A) Time, quality
B) Quality, resource
C) Cost, time
D) Quality, cost
E) Time, resource

Correct Answer

verifed

verified

All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.

Correct Answer

verifed

verified

All projects are usually either time-constrained or resource-constrained.

Correct Answer

verifed

verified

Showing 1 - 20 of 90