Integrating a project's work packages within the organization's management structure is known as work breakdown structure.

Correct Answer

verifed

verified

The tendency for the project deliverables to expand over time-usually by changing requirements,specifications,and priorities-is called


A) Scope erosion.
B) Scope creep.
C) Project bloat.
D) Scope enhancement.
E) Project add-ons.

Correct Answer

verifed

verified

All of the following are ways the WBS helps in managing projects EXCEPT


A) With cost and time estimates the WBS makes it possible to plan,schedule and budget the project.
B) It provides management with information appropriate to each level.
C) Can be used to define communication channels.
D) Allows the project manager to establish the overall objective of the project.
E) As it is developed,organizational units and individuals can be assigned responsibility of work packages.

Correct Answer

verifed

verified

All of the following are usually included in a work package EXCEPT


A) What will be done.
B) The time needed to complete the work.
C) A single person who is responsible for its completion.
D) All the costs for the work package.
E) All of these are included in a work package.

Correct Answer

verifed

verified

The result of subdividing the work of a project into smaller and smaller work elements is called a(n)__________.

Correct Answer

verifed

verified

work breakdown structure
Explanation: On...

View Answer

The gradual expansion of project requirements,specifications and priorities during the execution of project is known as ____________.

Correct Answer

verifed

verified

scope creep
Explanation: Scope describes...

View Answer

Project scope describes what you expect to deliver to your customers when the project is complete.

Correct Answer

verifed

verified

Scope creep can be reduced by carefully writing a(n)__________ statement.

Correct Answer

verifed

verified

scope
Explanation: A...

View Answer

A priority matrix helps project managers manage trade-offs among time,cost and performance or scope.This helps to identify which criterion is constrained,which should be enhanced and which can be accepted.Some argue that all of these criteria are always constrained.Agree or disagree? Explain why.

Correct Answer

verifed

verified

The last element of a project scope statement or checklist ensures an understanding and agreement of expectations.This is known as ____________.

Correct Answer

verifed

verified

reviews with customer
Explanat...

View Answer

The intersection of work packages and the organizational unit creates a project control point called a cost account.

Correct Answer

verifed

verified

For large companies,the organization breakdown structure is used rather than the work breakdown structure.

Correct Answer

verifed

verified

One of the primary jobs of a project manager is to manage the trade-offs associated with the project.Which of the following is NOT one of the basic classifications of project priorities?


A) Profit
B) Cost
C) Time
D) Performance
E) All of these are basic classifications

Correct Answer

verifed

verified

Define scope creep.When is it good? When is it bad? Provide real-life examples of both cases.

Correct Answer

verifed

verified

Which of the following is least likely to be included in a work package?


A) How long the work package should take to complete
B) A description of work to be performed
C) Overhead expenses
D) How much the work package should cost to complete
E) The person responsible for the work package

Correct Answer

verifed

verified

Scott has just been given a project that has a specific completion date.After a discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets.The completion date is best classified as


A) Constrained.
B) Reduced.
C) Accepted.
D) Limited.
E) Optional.

Correct Answer

verifed

verified

Having a strong communication plan can go a long way toward mitigating project problems.A communication plan should address all of the following EXCEPT


A) When the information will be communicated.
B) How information should be communicated and to whom.
C) What methods will be used to gather and store information.
D) What information needs to be collected and are there limits as to who has access to it.
E) All of these should be addressed in a communication plan.

Correct Answer

verifed

verified

The _________ is used to assist in making project trade-offs among schedule,budget,and performance objectives.


A) Responsibility matrix
B) Work breakdown structure
C) Project priority matrix
D) Work package
E) Criterion matrix

Correct Answer

verifed

verified

If a project is small and does not require an elaborate system to assign tasks,which of the following is a good choice?


A) Responsibility matrix
B) Organization breakdown structure
C) Work breakdown structure
D) Priority matrix
E) Process breakdown structure

Correct Answer

verifed

verified

"To construct a high-quality,custom home within five months at costs not to exceed $150,000" is best classified as


A) A deliverable.
B) A milestone.
C) An objective.
D) A limit.
E) An exclusion.

Correct Answer

verifed

verified