Filters
Question type

Study Flashcards

The table depicts an production line that has been balanced with a takt time of 2 minutes. Where would you add a worker if you wanted to increase the output rate while keeping six work stations?  Workstation 123456 Task A,BCD,E,FG,HIJ,K,L Time (min) 1,11.81,0.5,0.40.9,0.81.80.5,0.5,0.6\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Workstation } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Task } & \mathrm { A } , \mathrm { B } & \mathrm { C } & \mathrm { D } , \mathrm { E } , \mathrm { F } & \mathrm { G } , \mathrm { H } & \mathrm { I } & \mathrm { J } , \mathrm { K } , \mathrm { L } \\\hline \text { Time } ( \mathrm { min } ) & 1,1 & 1.8 & 1,0.5,0.4 & 0.9,0.8 & 1.8 & 0.5,0.5,0.6 \\\hline\end{array}


A) station 1
B) station 2
C) station 3
D) station 6

Correct Answer

verifed

verified

A manufacturing process decision affects:


A) the type of workforce needed.
B) the type of equipment needed.
C) the type of products that can be made.
D) All of the above are correct.

Correct Answer

verifed

verified

The greater the emphasis on intangible activities, the more management's attention will be directed to:


A) buildings and property.
B) training employees.
C) truck fleets.
D) material costs.

Correct Answer

verifed

verified

In a service package the greater the emphasis on intangible activities is, the more critical is the training and retention of skilled employees and the development and maintenance of the firm's knowledge assets.

Correct Answer

verifed

verified

According to the law of variability, converting from an assemble-to-order to a make-to-order production process should increase productivity of the manufacturing processes.

Correct Answer

verifed

verified

A customer service function at an insurance firm that handles claims based on the first letter of the customer's last name is an example of applying group technology to a service operation.

Correct Answer

verifed

verified

Capability variety is the difference in how customers view an identical service outcome. What some customers might view as economical and thrifty others might view as cheap and poor value.

Correct Answer

verifed

verified

Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units. Use this information to answer the following question(s) .  Task  Time (sec)  Predecessor J45 K 50 JL40 JM55 K, LN40MO65M P 25 N R 35O,P\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \mathrm { J } & 45 & \cdots \\\hline \text { K } & 50 & \mathrm {~J} \\\hline \mathrm { L } & 40 & \mathrm {~J} \\\hline \mathrm { M } & 55 & \mathrm {~K} , \mathrm {~L} \\\hline \mathrm { N } & 40 & \mathrm { M } \\\hline \mathrm { O } & 65 & \mathrm { M } \\\hline \text { P } & 25 & \mathrm {~N} \\\hline \text { R } & 35 & \mathrm { O } , \mathrm { P } \\\hline\end{array} -Refer to the scenario above. What is the theoretical minimum number of stations?


A) four
B) five
C) six
D) seven

Correct Answer

verifed

verified

An advantage of a production line process is:


A) higher volume of output needed to justify the investment.
B) greater degree of flexibility of the process.
C) lower per unit cost of items produced on the line.
D) higher range of output typically produced on such a process.

Correct Answer

verifed

verified

In stark contrast to a product layout, a(n)________ layout is better suited to environments where the process steps can change dramatically from one job or customer to the next.

Correct Answer

verifed

verified

What is the optimal location for these departments in the floor plan depicted if the departments have a daily number of trips between each other as shown? The total number of trips is accounted for in the table, so for example, the 16 trips between A and B are some combination of trips from A to B and from B to A. Daily Number of Trips Between Departments ABCDEFGHIA161893910314 B 41221019416 C 18388010 D 314157 E 1171512 F 19154 G 817 H 14 I \begin{array}{c|c|c|c|c|c|c|c|c|c} & \mathrm{A} & \mathrm{B} & \mathrm{C} & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline \mathrm{A} & \cdots & 16 & 18 & 9 & 3 & 9 & 10 & 3 & 14 \\\hline \text { B } & & \cdots & 4 & 12 & 2 & 10 & 19 & 4 & 16 \\\hline \text { C } & & & \cdots & 18 & 3 & 8 & 8 & 0 & 10 \\\hline \text { D } & & & & \cdots & 3 & 14 & 1 & 5 & 7 \\\hline \text { E } & & & & & \cdots & 1 & 17 & 15 & 12 \\\hline \text { F } & & & & & & \cdots & 19 & 15 & 4 \\\hline \text { G } & & & & & & & \cdots & 8 & 17 \\\hline \text { H } & & & & & & & & \cdots & 14 \\\hline \text { I } & & & & & & & & & \ldots\end{array} Floor Plan  Office Space 1 Office Space 4 Office Space 7 Office Space 2 Office Space 5 Office Space 8 Office Space 3 Office Space 6 Office Space 9\begin{array} { | l | l | l | } \hline \text { Office Space } 1 & \text { Office Space } 4 & \text { Office Space } 7 \\\hline \text { Office Space } 2 & \text { Office Space } 5 & \text { Office Space } 8 \\\hline \text { Office Space } 3 & \text { Office Space } 6 & \text { Office Space } 9 \\\hline\end{array} Distance Between Offices  Office Space 123456789110201014222022282101410142220223221410282220410201014225101410146221410710208109\begin{array}{|c|c|c|c|c|c|c|c|c|c}\hline \text { Office Space } & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 \\\hline 1 & - & 10 & 20 & 10 & 14 & 22 & 20 & 22 & 28 \\\hline 2 & & \cdots & 10 & 14 & 10 & 14 & 22 & 20 & 22 \\\hline 3 & & & \cdots & 22 & 14 & 10 & 28 & 22 & 20 \\\hline 4 & & & & \cdots & 10 & 20 & 10 & 14 & 22 \\\hline 5 & & & & & - & 10 & 14 & 10 & 14 \\\hline 6 & & & & & & \cdots & 22 & 14 & 10 \\\hline 7 & & & & & & & \cdots & 10 & 20 \\\hline 8 & & & & & & & & \cdots & 10 \\\hline 9 & & & & & & & & & \ldots \\\hline\end{array}

Correct Answer

verifed

verified

Multiple answers are possible; for examp...

View Answer

Champion Cooling has just signed a contract to assemble window air conditioners for another company. The list of tasks, including time requirements and immediate predecessors, follows. Each task may not be shortened. Initially, the plan was to make 300 units in an eight hour day but as the summer months approach, Champion Cooling finds themselves far behind in total production. They wish to reconfigure their production line in order to produce maximum output. What should their takt time be?  Task  Time (min)   Predecessor  Bolt compressor to base 5 None  Install coils and lines 6 Bolt compressor to base  Install fan motor 7 Install coils and lines  Install switch and thermostat 5 Install fan motor  Charge system and test 10 Install switch and thermostat  Cosmetic detailing 7 Charge system and test \begin{array} { | l | c | c | } \hline \text { Task } & \text { Time (min) } & \text { Predecessor } \\\hline \text { Bolt compressor to base } & 5 & \text { None } \\\hline \text { Install coils and lines } & 6 & \text { Bolt compressor to base } \\\hline \text { Install fan motor } & 7 & \text { Install coils and lines } \\\hline \text { Install switch and thermostat } & 5 & \text { Install fan motor } \\\hline \text { Charge system and test } & 10 & \text { Install switch and thermostat } \\\hline \text { Cosmetic detailing } & 7 & \text { Charge system and test } \\\hline\end{array}


A) 5
B) 6
C) 7
D) 10

Correct Answer

verifed

verified

Consider any collection of tasks to be assigned to stations in a line balancing exercise. Use the equation for determining the minimum number of stations to derive an upper bound on the efficiency of the actual line balance for those same tasks.

Correct Answer

verifed

verified

The minimum number of stations equation ...

View Answer

A sporting apparel manufacturer that produces t-shirts to commemorate significant athletic achievements for proud students and alumni probably uses:


A) a fixed position layout.
B) batch manufacturing.
C) a continuous flow process.
D) a production line.

Correct Answer

verifed

verified

The ________ includes all the value-added physical and intangible activities that a service organization provides to the customer.

Correct Answer

verifed

verified

The service package continuum ranges from immediate to delayed.

Correct Answer

verifed

verified

When designers are considering the ways that a space may be laid out with functional departments:


A) they typically construct every possible physical layout.
B) they don't construct every physical layout, but they do simulate every possible layout.
C) they usually look for a viable, but not optimal solution.
D) they assign layouts at random since it doesn't pay to consider a good layout.

Correct Answer

verifed

verified

Highly automated batch processes that can reduce the cost of making similar groups of products are:


A) functional layouts.
B) flexible manufacturing systems.
C) make-to-stock.
D) adjacent processes.

Correct Answer

verifed

verified

A manager deciding where six departments could be located in a six-room office building has over 500 possible arrangements.

Correct Answer

verifed

verified

Draw the product-process matrix and discuss the placement of each process type

Correct Answer

verifed

verified

The product process matrix relates outpu...

View Answer

Showing 41 - 60 of 100