Filters
Question type

Study Flashcards

With the backyard poultry craze unleashing a tidal wave of municipal code proposals, Chickenverks is poised to capitalize on the sudden demand for chicken tractors. The portable henhouses they have designed can be assembled in 10 basic steps, each with a required time and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 40 units per hour.  Task  Time (sec) Predecessor A25B35 AC20 AD55 BE45C,DF15 BG35CH40D,EJ25 F,GK30H,J\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \mathrm { A } & 25 & \cdots \\\hline \mathrm { B } & 35 & \mathrm {~A} \\\hline \mathrm { C } & 20 & \mathrm {~A} \\\hline \mathrm { D } & 55 & \mathrm {~B} \\\hline \mathrm { E } & 45 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & 15 & \mathrm {~B} \\\hline \mathrm { G } & 35 & \mathrm { C } \\\hline \mathrm { H } & 40 & \mathrm { D } , \mathrm { E } \\\hline \mathrm { J } & 25 & \mathrm {~F} , \mathrm { G } \\\hline \mathrm { K } & 30 & \mathrm { H } , \mathrm { J } \\\hline\end{array} Balance the line according to the longest operation rule and calculate the percent idle time. Using the same arrangement of tasks at work stations, what is the greatest output that can be achieved in an eight-hour day and what is the percent idle time of this design?

Correct Answer

verifed

verified

The takt time is 60 ∗ 60/40 = 90 seconds...

View Answer

The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time and predecessor as shown in the table. They work a 7 hour day and want to produce at a rate of 360 units per day. What should their takt time be?  Task  Time (sec)  Predecessor  A 45 B 50 A  C 40 A  D 55 B, C  E 40 D  F 65 D  G 25 E  H 35 F, G \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 40 & \text { A } \\\hline \text { D } & 55 & \text { B, C } \\\hline \text { E } & 40 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { F, G } \\\hline\end{array}


A) 70 seconds
B) 65 seconds
C) 52 seconds
D) 25 seconds

Correct Answer

verifed

verified

Name a service business that relies heavily on intangible activities. How does the level of intangibility fit with the degrees of contact and customization?

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

A service business that relies heavily o...

View Answer

In a service blueprint, the line of internal interaction falls between the customer and the onstage service provider.

Correct Answer

verifed

verified

The table depicts a production line that has been balanced with a takt time of 2 minutes. If you could hire another six workers, which of these systems would result in the highest output rate?  Workstation 123456 Task A,BCD,E,FG,HIJ,K,L Time (min) 1,11.81,0.5,0.40.9,0.81.80.5,0.5,0.6\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Workstation } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Task } & \mathrm { A } , \mathrm { B } & \mathrm { C } & \mathrm { D } , \mathrm { E } , \mathrm { F } & \mathrm { G } , \mathrm { H } & \mathrm { I } & \mathrm { J } , \mathrm { K } , \mathrm { L } \\\hline \text { Time } ( \mathrm { min } ) & 1,1 & 1.8 & 1,0.5,0.4 & 0.9,0.8 & 1.8 & 0.5,0.5,0.6 \\\hline\end{array}


A) simply duplicating the existing line so you had two lines doing exactly the same thing
B) assigning one worker to each activity and creating a single twelve station production line
C) keeping the existing balance and assigning three workers to stations 1, two workers to station 2, two workers to station 3, one worker to station 4, two workers to station 5, and two workers to station 6
D) you would be indifferent between alternatives A and B

Correct Answer

verifed

verified

Provide an example (other than the one offered in the text)of a supply chain composed of manufacturers using at least three different types of manufacturing processes.

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

An example of a supply chain composed of...

View Answer

These three tables show the floor layout of 5 departments in an office building, the average number of daily trips between each pair of offices, and the distance between each pair of offices. What is the total cost of this layout if there is a $0.50 per foot transportation cost? Average number of trips between departments  A  B  C  D  E  A 25152530 B 405035 C 1515D20 E \begin{array} { | l | c | c | c | c | c | } \hline & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } \\\hline \text { A } & \cdots & 25 & 15 & 25 & 30 \\\hline \text { B } & & \cdots & 40 & 50 & 35 \\\hline \text { C } & & & \cdots & 15 & 15 \\\hline \mathrm { D } & & & & \cdots & 20 \\\hline \text { E } & & & & & \cdots \\\hline\end{array} ABDCE\begin{array} { | l | l | l | } \hline \mathrm { A } & \mathrm { B } & \mathrm { D } \\\hline & \mathrm { C } & \mathrm { E } \\\hline\end{array} Distance between departments (feet)  A  B  C  D  E  A 20254045 B 52025 C 2520 D 5 E \begin{array} { | l | c | c | c | c | c | } \hline & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } \\\hline \text { A } & \cdots & 20 & 25 & 40 & 45 \\\hline \text { B } & & \cdots & 5 & 20 & 25 \\\hline \text { C } & & & \cdots & 25 & 20 \\\hline \text { D } & & & & \cdots & 5 \\\hline \text { E } & & & & & - \\\hline\end{array}


A) $460.00
B) $2300.00
C) $3037.50
D) $4785.50

Correct Answer

verifed

verified

Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.  Task  Time (sec)  Predecessor  A 45 B 50 A  C 20 A  D 55 A  E 15 D  F 65 D  G 25 E  H 35 B, C, F, G \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array} -Refer to the scenario above. What is the theoretical minimum number of stations that will be used if the line is balanced using the appropriate takt time?


A) 3
B) 4
C) 5
D) 6

Correct Answer

verifed

verified

Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.  Task  Time (sec)  Predecessor  A 45 B 50 A  C 20 A  D 55 A  E 15 D  F 65 D  G 25 E  H 35 B, C, F, G \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array} -Refer to the scenario above. The process design team realizes that the potential spike in demand for this device requires increased output. They elect to add a seventh worker to their production team at the first station. What is the net effect of adding this worker?


A) Nothing-the output rate does not change.
B) The output rate increases by 20%.
C) The output rate increases by 10%.
D) The output rate increases by 5%.

Correct Answer

verifed

verified

An assemble-to-order process occurs upstream from:


A) design.
B) material sourcing.
C) fabrication.
D) assembly/finishing.

Correct Answer

verifed

verified

Service operations compete and position themselves in the marketplace based on the three dimensions - ________, ________, and ________.

Correct Answer

verifed

verified

degree of customizat...

View Answer

A job shop manufacturing process is better suited to make a variety of products than a continuous flow process.

Correct Answer

verifed

verified

________ are products that are customized only at the very end of the manufacturing process.

Correct Answer

verifed

verified

Which of these manufacturing processes involves products that cannot be broken into discrete units?


A) job shop
B) batch
C) production line
D) continuous flow

Correct Answer

verifed

verified

What is the optimal location for these departments in the floor plan depicted if the transportation cost is $2 per foot and the departments have a daily number of trips between each other as shown? Daily Number of Trips Between Departments ABCDEA20406080B103050 C 015D5 E \begin{array} { | c | c | c | c | c | c | } \hline & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } & \mathrm { E } \\\hline \mathrm { A } & \cdots & 20 & 40 & 60 & 80 \\\hline \mathrm { B } & & \cdots & 10 & 30 & 50 \\\hline \text { C } & & & \cdots & 0 & 15 \\\hline \mathrm { D } & & & & \cdots & 5 \\\hline \text { E } & & & & & \cdots \\\hline\end{array} Floor Plan  Office Space 1 Office Space 2 Office Space 3 Office Space 4 Office Space 5\begin{array} { l | l | l | l | l } \hline \text { Office Space } 1 & \text { Office Space } 2 & \text { Office Space } 3 & \text { Office Space } 4 & \text { Office Space } 5 \\\hline\end{array} Distance Between Offices  Office Space 12345110203040210203031020455\begin{array} { | l | c | c | c | c | c | } \hline \text { Office Space } & 1 & 2 & 3 & 4 & 5 \\\hline \hline 1& \cdots & 10 & 20 & 30 & 40 \\\hline \hline2 & & \cdots & 10 & 20 & 30 \\\hline \hline 3& & & \cdots & 10 & 20 \\\hline \hline 4& & & & \cdots & 5 \\\hline 5 & & & & & \cdots \\\hline\end{array}

Correct Answer

verifed

verified

Multiple answers are possible; for examp...

View Answer

What are the four levels of customization and at what place does each occur in the supply chain?

Correct Answer

verifed

verified

The four levels ranked from least to gre...

View Answer

The table depicts a production line that has been balanced with a takt time of 2 minutes. What is the efficiency of this balance?  Workstation 123456 Task A,BCD,E,FG,HIJ,K,L Time (min) 1,11.81,0.5,0.40.9,0.81.80.5,0.5,0.6\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Workstation } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Task } & \mathrm { A } , \mathrm { B } & \mathrm { C } & \mathrm { D } , \mathrm { E } , \mathrm { F } & \mathrm { G } , \mathrm { H } & \mathrm { I } & \mathrm { J } , \mathrm { K } , \mathrm { L } \\\hline \text { Time } ( \mathrm { min } ) & 1,1 & 1.8 & 1,0.5,0.4 & 0.9,0.8 & 1.8 & 0.5,0.5,0.6 \\\hline\end{array}


A) 82.5%
B) 85%
C) 87.5%
D) 90%

Correct Answer

verifed

verified

The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units using seven workers-one for each station.  Task  Time (sec) Predecessor J45 K 50 J L 40 J M 55 K, LN40M O 65M P 25 N R 35O,P\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \mathrm { J } & 45 & \cdots \\\hline \text { K } & 50 & \mathrm {~J} \\\hline \text { L } & 40 & \mathrm {~J} \\\hline \text { M } & 55 & \mathrm {~K} , \mathrm {~L} \\\hline \mathrm { N } & 40 & \mathrm { M } \\\hline \text { O } & 65 & \mathrm { M } \\\hline \text { P } & 25 & \mathrm {~N} \\\hline \text { R } & 35 & \mathrm { O } , \mathrm { P } \\\hline\end{array} Balance the line according to the longest operation rule and calculate the percent idle time. Using the same arrangement of tasks at work stations, what is the greatest output that can be achieved in an eight-hour day and what is the percent idle time of this design?

Correct Answer

verifed

verified

The takt time is 8 ∗ 60 ∗ 60/400 = 72 se...

View Answer

No manufacturing process can be best at everything.

Correct Answer

verifed

verified

Where should a business consultant position herself on the three axes of contact, customization, and cost.

Correct Answer

verifed

verified

Consultancy services are by their very n...

View Answer

Showing 61 - 80 of 100

Related Exams

Show Answer