Filters
Question type

Study Flashcards

Which of the following is not a major input into capacity requirements planning (CRP) ?


A) planned order releases
B) routing file
C) load profiles for each work center
D) open orders file

Correct Answer

verifed

verified

A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.   If L4L ordering is used the planned order releases would be A) 40 in period 1 and 0 in period 3 B) 80 in period 2 and 60 in period 3 C) 60 in period 2 and 80 in period 3 D) 0 in period 1 and 40 in period 3 If L4L ordering is used the planned order releases would be


A) 40 in period 1 and 0 in period 3
B) 80 in period 2 and 60 in period 3
C) 60 in period 2 and 80 in period 3
D) 0 in period 1 and 40 in period 3

Correct Answer

verifed

verified

______________ is a lot sizing technique that orders for multiple demand periods is referred to as


A) Lot-for-lot (L4L)
B) Periodic order quantity (POQ)
C) Economic order quantity(EOQ)
D) Multiple order quantity (MOQ)

Correct Answer

verifed

verified

ERP application modules can be used alone or in combination.

Correct Answer

verifed

verified

One objective of material requirements planning (MRP)is to utilize all available capacity.

Correct Answer

verifed

verified

Capacity requirements planning (CRP)projects the load from a given material plan onto the capacity of a system.

Correct Answer

verifed

verified

The master production schedule (MPS)is a major output of the MRP process.

Correct Answer

verifed

verified

A phantom bill of material is used


A) to group small,loose parts together.
B) when the product is manufactured in major subassemblies.
C) for subassemblies that are immediately consumed in the next stage of production.
D) when due dates have not been calculated.

Correct Answer

verifed

verified

Given the following Product Structure Record Given the following Product Structure Record   The number of E's required for each A would be A) 1 B) 2 C) 3 D) 4 The number of E's required for each A would be


A) 1
B) 2
C) 3
D) 4

Correct Answer

verifed

verified

Planned order releases at one level of a product structure generate gross requirements at the next level.

Correct Answer

verifed

verified

A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.   If the periodic order quantity lot sizing rule is used,then planned order releases in Period 2 would be A) 40 in period 1 B) 60 in period 2 C) 120 in period 3 D) 140 in Period 2 If the periodic order quantity lot sizing rule is used,then planned order releases in Period 2 would be


A) 40 in period 1
B) 60 in period 2
C) 120 in period 3
D) 140 in Period 2

Correct Answer

verifed

verified

A matrix is used to organize and display the information generated by the MRP process.

Correct Answer

verifed

verified

Given the following Product Structure Record Given the following Product Structure Record   The number of D's required for each A would be A) 2 B) 3 C) 6 D) 12 The number of D's required for each A would be


A) 2
B) 3
C) 6
D) 12

Correct Answer

verifed

verified

Firms that successfully implement an MRP system no longer require cycle counting of inventory.

Correct Answer

verifed

verified

Customer relationship management (CRM)software plans and executes business processes that involve customer interactions.

Correct Answer

verifed

verified

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 4 would be A) 270 B) 290 C) 340 D) 560 If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 4 would be


A) 270
B) 290
C) 340
D) 560

Correct Answer

verifed

verified

An enterprise resource planning (ERP)system shares information across functional areas.

Correct Answer

verifed

verified

Given the following Product Structure Record Given the following Product Structure Record   The number of E's required for each A would be A) 3 B) 6 C) 12 D) 24 The number of E's required for each A would be


A) 3
B) 6
C) 12
D) 24

Correct Answer

verifed

verified

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,the periodic order quantity would be A) 3 periods of requirements B) 2 periods of requirements C) 1 period of requirements D) 0 period of requirements If each order cost $500 and the holding cost is $0.75 per item per period,the periodic order quantity would be


A) 3 periods of requirements
B) 2 periods of requirements
C) 1 period of requirements
D) 0 period of requirements

Correct Answer

verifed

verified

37.All of the following are inputs into the MRP process except


A) the master production schedule.
B) the product structure file.
C) the item master file.
D) the planned order report.

Correct Answer

verifed

verified

Showing 61 - 80 of 82

Related Exams

Show Answer