A) is effective for companies with multiple large projects.
B) is appropriate only in construction firms.
C) often fails when the project cuts across organizational lines.
D) is only appropriate for technical projects.
E) is especially useful for small project.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) Level 1,Level 2,Level 4,Level 3,Level 3
B) Level 1,Level 2,Level 3,Level 4,Level 5
C) Level 0,Level 1,Level 2,Level 3,Level 4
D) Level 0,Level 2,Level 2,Level 3,Level 3
E) Level 0,Level 1,Level 1,Level 2,Level 3
Correct Answer
verified
Multiple Choice
A) PERT is more accurate than CPM.
B) PERT assumes that activity durations are known.
C) PERT ignores activity costs.
D) CPM assumes that activity durations can vary.
E) they differ in terminology and in the construction of the network.
Correct Answer
verified
Multiple Choice
A) $500.
B) $1,500.
C) $750.
D) $13,000.
E) $15,000.
Correct Answer
verified
Multiple Choice
A) 98.
B) 112.
C) 120.
D) 124.
E) 220.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Gantt charts give a timeline and precedence relationships for each activity of a project.
B) Gantt charts use the four standard spines of Methods,Materials,Manpower,and Machinery.
C) Gantt charts are visual devices that show the duration of activities in a project.
D) Gantt charts are expensive.
E) Gantt charts identify the critical path.
Correct Answer
verified
Multiple Choice
A) PERT
B) CPM
C) Gantt Chart
D) either PERT or CPM
E) PERT,CPM,or a Gantt chart are fine
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 5.00.
B) 5.33.
C) 5.67.
D) 17.00.
E) 0.533.
Correct Answer
verified
Multiple Choice
A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical and has zero slack.
E) F is critical and has zero slack.
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Each activity has two estimates of its duration.
B) Project variance is the sum of all activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) Only non-critical activities contribute to the project variance.
Correct Answer
verified
Multiple Choice
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths through this network.
E) There is no critical path in this network.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of given times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 41 - 60 of 122