A project organization


A) is effective for companies with multiple large projects.
B) is appropriate only in construction firms.
C) often fails when the project cuts across organizational lines.
D) is only appropriate for technical projects.
E) is especially useful for small project.

Correct Answer

verifed

verified

Describe the differences between a Gantt chart and a PERT/CPM network.

Correct Answer

verifed

verified

The differences between a Gant...

View Answer

The shortest of all paths through the network is the critical path.

Correct Answer

verifed

verified

Match the following steps in Microsoft's development of Windows 7 to their respective WBS level. Step Level Develop Windows 7 OS ? System Testing ? Compatible with Windows XP ? Develop GUI's ? Module Testing ?


A) Level 1,Level 2,Level 4,Level 3,Level 3
B) Level 1,Level 2,Level 3,Level 4,Level 5
C) Level 0,Level 1,Level 2,Level 3,Level 4
D) Level 0,Level 2,Level 2,Level 3,Level 3
E) Level 0,Level 1,Level 1,Level 2,Level 3

Correct Answer

verifed

verified

The main difference between PERT and CPM is that


A) PERT is more accurate than CPM.
B) PERT assumes that activity durations are known.
C) PERT ignores activity costs.
D) CPM assumes that activity durations can vary.
E) they differ in terminology and in the construction of the network.

Correct Answer

verifed

verified

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,the crash cost per period is


A) $500.
B) $1,500.
C) $750.
D) $13,000.
E) $15,000.

Correct Answer

verifed

verified

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day (rounded to nearest day)


A) 98.
B) 112.
C) 120.
D) 124.
E) 220.

Correct Answer

verifed

verified

The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.

Correct Answer

verifed

verified

Which of the following statements regarding Gantt charts is true?


A) Gantt charts give a timeline and precedence relationships for each activity of a project.
B) Gantt charts use the four standard spines of Methods,Materials,Manpower,and Machinery.
C) Gantt charts are visual devices that show the duration of activities in a project.
D) Gantt charts are expensive.
E) Gantt charts identify the critical path.

Correct Answer

verifed

verified

A project manager is interested in crashing a project with variable activity times.Which of the following tools should he/she employ?


A) PERT
B) CPM
C) Gantt Chart
D) either PERT or CPM
E) PERT,CPM,or a Gantt chart are fine

Correct Answer

verifed

verified

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

Correct Answer

verifed

verified

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.Its expected time is


A) 5.00.
B) 5.33.
C) 5.67.
D) 17.00.
E) 0.533.

Correct Answer

verifed

verified

Activity D on a CPM network has predecessors B and C,and has successor F.D has duration 6.B's earliest finish is 18,while C's is 20.F's late start is 26.Which of the following is definitely true?


A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical and has zero slack.
E) F is critical and has zero slack.

Correct Answer

verifed

verified

In PERT analysis,the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.

Correct Answer

verifed

verified

________ is an organization formed to ensure that programs (projects)receive the proper management and attention.

Correct Answer

verifed

verified

Project or...

View Answer

Which of the following statements regarding PERT analysis is true?


A) Each activity has two estimates of its duration.
B) Project variance is the sum of all activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) Only non-critical activities contribute to the project variance.

Correct Answer

verifed

verified

A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.


A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths through this network.
E) There is no critical path in this network.

Correct Answer

verifed

verified

The network analysis method that allows activity times to vary is ________.

Correct Answer

verifed

verified

PERT or Pr...

View Answer

Activity R on a CPM network has predecessors M and N,and has successor S.R has duration 5.N's late finish is 18,while M's is 20.S's late start is 14.Which of the following is definitely true?


A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of given times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.

Correct Answer

verifed

verified

The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.

Correct Answer

verifed

verified

Showing 41 - 60 of 122