Asked by
kundan kumar
on Dec 09, 2024Verified
A four-year project has an initial outlay of $100,000. The future cash inflows from its project are $50,000 for years one and two and $40,000 for years three and four. Given a discount rate of 10%, will the project be accepted?
A) Accept the project as the NPV is $44,150.
B) Reject the project as the NPV is $44,150.
C) Reject the project as the NPV is $(44,150) .
D) Accept the project as the NPV is $18,250.
E) Reject the project as the NPV is $18,250.
Initial Outlay
The initial investment amount required to start a project or purchase an asset.
Future Cash Inflows
Expected incoming funds or earnings generated from investments, operations, or financial activities in the future.
Discount Rate
The discount rate that's used to estimate the present value of future cash flows within discounted cash flow analysis.
- Acquire knowledge of Net Present Value (NPV) and its critical importance in determining investment strategies.
Verified Answer
EN
Learning Objectives
- Acquire knowledge of Net Present Value (NPV) and its critical importance in determining investment strategies.