Asked by

kundan kumar
on Dec 09, 2024

verifed

Verified

A four-year project has an initial outlay of $100,000. The future cash inflows from its project are $50,000 for years one and two and $40,000 for years three and four. Given a discount rate of 10%, will the project be accepted?

A) Accept the project as the NPV is $44,150.
B) Reject the project as the NPV is $44,150.
C) Reject the project as the NPV is $(44,150) .
D) Accept the project as the NPV is $18,250.
E) Reject the project as the NPV is $18,250.

Initial Outlay

The initial investment amount required to start a project or purchase an asset.

Future Cash Inflows

Expected incoming funds or earnings generated from investments, operations, or financial activities in the future.

Discount Rate

The discount rate that's used to estimate the present value of future cash flows within discounted cash flow analysis.

  • Acquire knowledge of Net Present Value (NPV) and its critical importance in determining investment strategies.
verifed

Verified Answer

EN
Ebonee NicholsDec 10, 2024
Final Answer:
Get Full Answer