An) _____ organizes the risks that have been identified into categories using a table with increasing levels of detail to the right.
A) master schedule
B) risk breakdown structure
C) control chart
D) risk management plan
E) risk response plan
Risk Breakdown Structure
A hierarchical decomposition of risks into categories and subcategories within a project or organization.
Master Schedule
A comprehensive plan that outlines the key activities and timelines necessary to complete a project or operation within the specified time frame.
Control Chart
A graphical tool used to monitor changes and trends in a process over time, helping to identify variations that may indicate problems or areas for improvement.
- Learn about the process and significance of risk evaluation and the construction of a risk breakdown structure.
Verified Answer
AD
Learning Objectives
- Learn about the process and significance of risk evaluation and the construction of a risk breakdown structure.