Concrete Company agrees to lay a foundation for Diamond Properties, but fails to finish the job. Diamond hires Earth Projects Inc. to complete the work. In a suit for breach, Diamond may recover from Concrete
A) nothing.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.
Complete Construction
The process of finishing a building or construction project in all its parts, fully executed according to the plan and specifications.
Suit
A legal action taken by one party against another in a court of law.
- Ascertain and investigate several compensations for breach of agreements, namely specific performance and agreed-upon damages.
Verified Answer
DM
Learning Objectives
- Ascertain and investigate several compensations for breach of agreements, namely specific performance and agreed-upon damages.