Dillon has a standard of 2 hours of labor per unit at $12 per hour. In producing 2000 units Dillon used 3850 hours of labor at a total cost of $46970. Dillon's labor quantity variance is
A) $770 U.
B) $770 F.
C) $1800 F.
D) $1930 F.
Labor Quantity Variance
This term measures the difference between the actual quantity of labor used and the expected (or standard) amount, multiplied by the standard labor rate, often used in cost accounting.
- Calculate the total overhead discrepancy, along with labor price and volume variances, and price and volume variances of materials.
Verified Answer
RC
Learning Objectives
- Calculate the total overhead discrepancy, along with labor price and volume variances, and price and volume variances of materials.