If the critical path is shorter than the project duration, the project has a negative total float.
Critical Path
The sequence of tasks that determines the minimum project duration; delaying any task on this path delays the whole project.
Project Duration
The total period from the start to the completion of a project.
Negative Total Float
The amount of time that needs to be saved on a project schedule to meet the deadline, indicating a project is behind schedule.
- Comprehend the concepts of critical path, total float, and project duration.
Verified Answer
RB
Learning Objectives
- Comprehend the concepts of critical path, total float, and project duration.
Related questions
Compressing the Task Durations Along the Critical Path to Meet ...
The _____ Establishes Key Dates Throughout the Life of a ...
A Simple CPM Network Has Three Activities, A, B, and ...
Which of the Following Statements Regarding CPM Networks Is True ...
Activity D on a CPM Network Has Predecessors B and ...