On projects with a low complexity level, the project manager and team leaders can make decisions:

A) during monthly staff meetings.
B) using well-documented decision-making procedures.
C) informally, with short meetings or phone calls.
D) on their own, without including the clients.
E) without recording the changes in project plans.

Low Complexity Level

Projects or tasks that are simple and straightforward to complete, often requiring minimal resources and less intricate planning.

Decision-making Procedures

Systematic approaches or methods employed to make choices among various alternatives to guide actions toward achieving a goal.