Asked by
David Trevino
on Oct 19, 2024Verified
A project can have _____, which means the calculated completion date of the last activity is later than the targeted completion date established at the beginning of the project.
A) a late start
B) lead time
C) lag time
D) an early start
E) negative float
Negative Float
The amount of time that must be saved in order to complete a project on schedule, indicating a project is behind its planned timeline.
- Acquire knowledge about the concepts of lead, lag, and float times and their consequences for project schedule management.
- Discover the approaches and justifications for advancing the schedule of a project.
Verified Answer
ZH
Learning Objectives
- Acquire knowledge about the concepts of lead, lag, and float times and their consequences for project schedule management.
- Discover the approaches and justifications for advancing the schedule of a project.