_____ is the difference between the finish date of the last activity on the critical path and the project completion date.
A) Lag time
B) Control limit
C) Total float
D) Contingency time
E) Forward pass
Total Float
The amount of time that a project task can be delayed without causing a delay to the project's overall completion date.