Asked by

Nasir popal
on Oct 31, 2024

verifed

Verified

Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?

A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of given times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.

CPM Network

A project management tool that uses Critical Path Method (CPM) for planning, scheduling, and controlling complex projects by identifying critical and non-critical tasks.

Predecessors

Entities or elements that precede others in a sequence or process, often used in project management to denote tasks that must be completed before others can start.

Successor

An entity or person that follows another in a specific role, position, or title, inheriting responsibilities or assets.

  • Utilize understanding of Critical Path Method to evaluate project timelines and pinpoint key tasks.
verifed

Verified Answer

AW
Alice WoodrowNov 04, 2024
Final Answer:
Get Full Answer