Asked by

Manny Williams
on Oct 31, 2024

verifed

Verified

The critical path for the network activities shown below is ________ with duration ________.  Activity  Duration  Immediate  Predecessors  A 10−− B 8−− C 2 A  D 4 A  E 5 B, C, D \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Duration } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 10 & - - \\\hline \text { B } & 8 & - - \\\hline \text { C } & 2 & \text { A } \\\hline \text { D } & 4 & \text { A } \\\hline \text { E } & 5 & \text { B, C, D } \\\hline\end{array} Activity  A  B  C  D  E  Duration 108245 Immediate  Predecessors  A  A  B, C, D 

A) A-C; 12
B) A-D-E; 19
C) B-E; 13
D) A-B-C-D-E; 29
E) A-B-C; 20

Critical Path

The sequence of stages determining the minimum time required to complete a project, identifying tasks that directly impact the project duration.

Immediate Predecessors

The tasks or activities that must be completed directly before a specific activity can start, in a project or process sequence.

Activity Duration

The total time period required to complete a specific task or activity within a project, from start to finish.

  • Apply knowledge of CPM to analyze project duration and identify critical activities.
verifed

Verified Answer

JR
Justin RobertsOct 31, 2024
Final Answer:
Get Full Answer