An) _____ has no duration or resources, and is simply an indicator of an important point in the project.

A) node
B) milestone
C) inference
D) hierarchy
E) attribute

Milestone

A significant event or point in a project, program, or portfolio that marks a major achievement or a phase of progress.

  • Identify and describe different components and tools used in project scheduling like milestones, calendars, and schedules.