To consider the availability of team members, consultants, and key pieces of equipment, you can create an) _____ which indicates working days and days off for a group or individual.
A) resource calendar
B) project calendar
C) task calendar
D) hierarchical calendar
E) base calendar
Resource Calendar
A calendar that documents the availability, working hours, holidays, and assignments of resources necessary for project completion.
Working Days
Days designated for work, typically excluding weekends and public holidays.
- Define and explain the different components and aids used in the crafting of project timelines, including milestones, calendars, and schedules.
- Grasp the significance of resource allocation and leveling in the context of project management.
Verified Answer
NK
Learning Objectives
- Define and explain the different components and aids used in the crafting of project timelines, including milestones, calendars, and schedules.