Asked by

erika shockley
on Oct 31, 2024

verifed

Verified

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

ES (Earliest Start)

The earliest point in time at which a task, project, or activity can begin, taking into account the completion of preceding tasks and any necessary waiting periods.

EF (Earliest Finish)

In project management, it is the earliest possible point in time when a particular task or activity can be completed, considering the start time and the duration of the task.

Predecessor

A task or activity that must be completed before a subsequent task or activity can begin in project management and scheduling contexts.

  • Acquire knowledge about the successive phases of managing projects and the tools used to strategize and schedule these initiatives.
verifed

Verified Answer

VJ
Veronica JuradoNov 03, 2024
Final Answer:
Get Full Answer