Asked by
Makaila Bowes
on Oct 19, 2024Verified
The _____ is the process of determining the earliest starting date for each activity by beginning at the project start date and adding the activity durations resulting with the early finish date for the project.
A) contingency time
B) span of control
C) master schedule
D) forward pass
E) milestone schedule
Forward Pass
A technique used in project management that involves calculating the earliest start and finish times for each task in a project schedule.
- Gain an understanding of the core concepts involved in project scheduling and planning.
- Learn the steps for updating and overseeing the project agenda to ensure effective time stewardship.
Verified Answer
SS
Learning Objectives
- Gain an understanding of the core concepts involved in project scheduling and planning.
- Learn the steps for updating and overseeing the project agenda to ensure effective time stewardship.