The _____ is the process of determining the earliest starting date for each activity by beginning at the project start date and adding the activity durations resulting with the early finish date for the project.

A) contingency time
B) span of control
C) master schedule
D) forward pass
E) milestone schedule

Forward Pass

A technique used in project management that involves calculating the earliest start and finish times for each task in a project schedule.