An updated schedule that shows the present status of the project is called the _____ schedule.

A) performance index
B) master
C) milestone
D) general conceptual
E) current

Current Schedule

The latest version of the project schedule, reflecting all known updates, changes, and progress.

  • Differentiate among various schedule categories (master, milestone, current) and their applications.
  • Understand the process of updating and controlling the project schedule to manage time effectively.