The _____ schedule is a summary level schedule that encompasses the entire project scope.

A) original
B) milestone
C) procurement
D) master
E) conceptual

Master Schedule

A comprehensive timeline that outlines all major tasks and milestones within a project, serving as a roadmap for execution.

  • Identify the differences among master, milestone, and current schedules, along with their respective functions.
verifed

Verified Answer